August 2026 Kaufman County Transportation Report

Page 1

Kaufman County Transportation Report August 2026

PROJECT STATUS UPDATES • • • • • • • • • • • • • • • • • • • • • • • •

Project Funding Summary ............................................................... 2 FM 548 (IH 20 to FM 1641) ................................................................... 3 FM 548 North: Phase I..................................................................... 4 FM 548 North: Phase II .................................................................... 6 FM 1641 ........................................................................................ 7 FM 741 .......................................................................................... 8 FM 741 Breakout ............................................................................ 9 FM 741 at US 175 ......................................................................... 10 Helms Trail .................................................................................. 11 SH 205 South ............................................................................... 12 I-20 Frontage Roads Terrell ........................................................... 13 I-20 Frontage Roads Kaufman ...................................................... 14 US 80 Widening ............................................................................ 15 US 80/Spur 557 (FM 460 to IH 20)....................................................... 17 Outer Loop .................................................................................. 18 FM 740/FM 460 ............................................................................ 19 US 175 Grade Separations Kemp................................................... 20 US 175 Feasibility Study ............................................................... 21 FM 148 ........................................................................................ 22 US 80 .......................................................................................... 23 SH 198 ........................................................................................ 24 SH 243 Safety Improvements ........................................................ 26 Glossary of Acronyms .................................................................. 28 TxDOT Funding Categories ............................................................ 29

Kaufman County Transportation Report August 2026

Prepared by:

1


| PROJECT FUNDING SUMMARY | PROJECT

COUNTY

OTHER

TOTAL COST

FM 548 (IH 20 to FM 1641)

$2,880,808

TBD

$93,380,808

FM 548 North: Phase I

$5,985,718

$125,999,853

$143,300,865

FM 548 North: Phase II

$1,542,811

$3,783,203

$95,906,919

FM 1641

$5,559,918

$6,668,519

$121,400,696

FM 741

$552,693

$4,974,241

$111,410,029

FM 741 Breakout

$0

$15,051,795

$15,051,795

FM 741 at US 175

$1,026,918

$315,000

$10,973,061

Helms Trail

$1,680,492

$0

$39,930,492

SH 205 South

$934,255

$134,051,075

$134,985,330

I-20 Frontage Roads Terrell

$0

TBD

$382,746,499

I-20 Frontage Roads Kaufman

$0

TBD

$189,612,460

US 80 Widening

$567,169

$151,379,089

$151,946,258

US 80 (FM 460 to Spur 557)

$0

TBD

$1,196,508,338

Outer Loop

$7,779,903

TBD

$2,243,899,183

FM 740/FM 460

$3,447,966

TBD

$139,254,681

US 175 Grade Separations Kemp

$1,552,105

TBD

$95,846,588

US 175 Feasibility Study

TBD

TBD

TBD

FM 148

$2,620,000

TBD

$87,395,625

US 80

$0

$98,459,060

$98,459,060

SH 198

$0

$4,926,222

$5,180,451

SH 243 Safety Improvements

$0

TBD

$3,357,961

TOTAL

$36,150,756

$545,608,057

$5,360,547,099

Kaufman County Transportation Report August 2026

Prepared by:

2


FM 548

2019

CSJ:

1091-02-025; 2588-01-025

Schematic Approval:

September 5, 2025

Limits:

from IH 20 to FM 1641

Environmental Approval:

October 2026

Project Description:

reconstruct FM 740 and FM 548 to 4lane divided urban roadways; bridge widening at Mustang Creek crossing

ROW Acquisition Complete:

*

Estimated Construction Cost:

$90,500,000

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

*

Engineer & Key Contact:

Jacobs, Abe Bekele

Let Date:

*

TxDOT Project Manager:

Grace Lo

Start Date:

*

Current Activity: • •

Schematic: Jacobs submitted a revised schematic to accommodate a median opening and turn lanes as requested by the public. Environmental: All environmental reports have been approved. Public Hearing was held on April 16, 2026. A draft comment response form was submitted to TxDOT for review on May 16, 2026. TxDOT approved conformity report. Awaiting environmental clearance.

Kaufman County Transportation Report August 2026

Prepared by:

3


FM 548 North: Phase I

2013

CSJ:

2588-01-022

Schematic Re-Approval:

December 28, 2018

Limits:

From north of US Highway 80 to Windmill Farms Blvd.

Environmental Clearance:

July 3, 2019

Construction Cost:

$80,359,417

ROW Acquisition Completed:

January 2023

Utility Relocations Complete:

August 2026

Construction Funding:

$121,437,325

CAT 1: $6,192,282 CAT 2: $115,245,043

Project Description:

Widen existing 2-lane, undivided facility to a 4- to 6-lane, divided facility

100% Plans:

December 2024

Commissioner:

Skeet Phillips, Precinct 2

Let Date:

March 5, 2025

Engineer & Key Contact:

Westwood, Mark Zoellner, Mark Schluter

Construction Start:

September 2025

TxDOT Project Manager:

Cody Jolley

Construction Completion:

May 2028

Current Activity: •

•

Utilities: Utilities that are clear of construction: Farmers Electric CoOp, City of Forney, High Point WSC, NTMWD, Oncor, and People’s Telephone Co-Op. Status of utilities currently in conflict: o AT&T: Relocations underway. o Atmos: Relocations underway. Anticipate completion at the end of August. Construction: Project let for construction on March 5, 2025. The project was awarded to Granite Construction Company with a low bid of $80,359,417 at 19.1% below the engineer’s estimate. There are 774 working days and 32 months of barricades. Pre-construction meeting was held on September 3, 2025. Construction began on September 8, 2025. See attached TxDOT construction report.

Kaufman County Transportation Report August 2026

Prepared by:

4


TxDOT Monthly Project Report for Kaufman County Date of report: August 17, 2026 Report prepared by: Cody Jolley, P.E.

Control: 2588-01-022 Limits: FM 548 North of US80 – Windmill Farms Blvd. Project: 2588-1-22 Highway: FM 548 Contractor: Granite Construction Company TxDOT Area Engineer: Nic Wadlington, P.E. TxDOT Assistant Area Engineer: Cody Jolley, P.E. TxDOT Project Engineer: Kyle Price, P.E. Contractor’s Superintendent: Darrol Camp

Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 962-3617 Phone: (972) 874-8724

Date Work Began: September 8, 2025 Anticipated Completion Date: May 2028

Current activities include: Excavation/Embankment. Culvert extensions. Drainage installation. Construct temporary pavement. Permanent asphalt underlayment. Concrete pavement. Narrative description of last month’s activities: Excavation/Embankment. Culvert extensions. Drainage installation. Construct temporary pavement. Permanent asphalt underlayment. Narrative description of activities planned for next month: Excavation/Embankment. Culvert extensions. Drainage installation. Construct temporary pavement. Permanent asphalt underlayment. Concrete pavement. Traffic issues: N/A Plans for changes in traffic patterns: N/A Item(s) of work currently controlling project completion: N/A Other items of significance: N/A

Kaufman County Transportation Report August 2026

Prepared by:

5


FM 548 North: Phase II

TxDOT

CSJ:

2588-01-017 (Kaufman County) 2588-02-008 (Rockwall County)

Schematic Re-Approval:

December 28, 2018

Limits:

From Windmill Farms Blvd. to SH 205

Environmental Clearance:

July 3, 2019

ROW Acquisition Completed:

August 2022

Estimated Construction Cost:

$90,580,905

$73,501,783: Kaufman County segment $17,079,122: Rockwall County segment

Construction Funding:

$0

Utility Relocations Complete:

June 2027

Project Description:

Widen existing 2-lane, undivided facility to a 4 to 6-lane, divided facility

100% Plans:

October 2026

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

June 2027

Engineer & Key Contact:

Burns & McDonnell, Tony Schmitt

Let Date:

Pending Funding

TxDOT Project Manager:

Gutema Gebrial

Construction Start:

*

Current Activity: • • •

PS&E: Burns & McDonnell continues working toward completion of 100% plans. Utilities: Utilities that are clear: Atmos, City of Dallas Water, Optimum, and Sprint. The status of utilities in conflict is below: o FEC: Relocations underway. o High Point SUD: Working on relocation plans. o Spectrum: Plans approved. Pending FEC relocations.

Kaufman County Transportation Report August 2026

Prepared by:

6


FM 1641

2013

CSJ:

1217-01-019; 2588-01-020

Schematic Re-Approval:

April 26, 2021

Limits:

From FM 548 to FM 148

Environmental Clearance:

August 31, 2021

ROW Acquisition Completed:

October 2023

Estimated Const. Cost:

$109,172,259

-019: $105,555,131 -020: $3,617,128

Construction Funding:

$0

Utility Relocations Complete:

December 2027

Project Description:

Widen to a 4-lane divided (6-lane ultimate) urban facility

100% Plans:

August 2025

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

December 2027

Engineer & Key Contact:

LTRA, Massoud Manesh

Let Date:

Pending Funding

TxDOT Project Manager:

Chaikou Bah

Construction Start:

*

Current Activity: • Utilities: Utilities that are clear: Atmos, Forney ISD, Gulf South Pipeline, Oncor, and Peoples Telephone. • Status of utilities in conflict is below. o AT&T: Relocations are underway. o City of Forney: Permit has been approved. Pending SIB loan. Anticipate advertisement of bid in December 2026. o Gastonia: Pending permit submission. Anticipate completion of relocations in November 2026. o NTMWD: Relocation plans submitted. Utility agreement is underway. o Suddenlink (Optimum): Relocations underway. Anticipate splicing to begin in September 2026. o Talty SUD: Relocation plans approved. Utility agreement underway. Anticipate completion of relocations in December 2026. o TVEC: Relocations are complete; pole removal remains.

Kaufman County Transportation Report August 2026

Prepared by:

7


FM 741

TxDOT

CSJ:

1092-01-021

Schematic Approval:

July 20, 2022

Limits:

from FM 548 to Spring Creek Blvd

Environmental Clearance:

March 28, 2023

Project Description:

Widen and reconstruct from a 2-lane rural undivided to a 4/6-lane urban divided

ROW Acquisition Complete:

June 2029

Estimated Constr. Cost:

$105,883,095

Utility Relocations Complete:

June 2031

Construction Funding:

$0

100% Plans:

September 2027

Commissioner:

Skeet Phillips, Precinct 2 and Tommy Moore, Precinct 4

Ready to Let Date:

June 2031

Engineer & Key Contact:

HNTB, Kyle Riley

Let Date:

Pending Funding

TxDOT Project Manager:

Solomon Robelie

Construction Completion:

*

Current Activity: • PS&E: Breakouts have been divided into 3 segments: 1092-01-029 (from Spring Creek Boulevard to north of Griffin Lane); 1092-01-030 (from north of Griffin Lane to IH 20); and 1092-01-031 (from IH 20 to FM 548). HNTB is working toward completion of final plan sets. • ROW: There are 124 parcels to acquire. There are 27 parcels remaining for acquisition. ROW acquisition efforts are underway for 1092-01-030. There are 6 parcels to acquire for that segment; parcels are expected to be acquired by March 2027. Other segments are on hold for now. • Utilities: TxDOT is in the process of verifying utility conflicts.

Kaufman County Transportation Report August 2026

Prepared by:

8


FM 741 Breakout

TxDOT

CSJ:

1092-01-026

Schematic Approval:

July 20, 2022

Limits:

from US 175 to Spring Creek Blvd

Environmental Clearance:

March 28, 2023

Project Description:

Widen and reconstruct from a 2-lane rural undivided to a 4/6-lane urban divided

ROW Acquisition Complete:

December 2025

Estimated Constr. Cost:

$13,439,103

Utility Relocations Complete:

December 2026

100% Plans:

June 2026

Construction Funding:

$15,051,795

$1,046,588: CAT 5 $14,005,207: CAT 7

Commissioner:

Tommy Moore, Precinct 4

Ready to Let Date:

December 2026

Engineer & Key Contact:

HNTB, Kyle Riley

Let Date:

May 2027

TxDOT Project Manager:

Solomon Robelie

Construction Completion:

*

Current Activity: • PS&E: HNTB has completed final plan set. • Utilities: Utilities found to be not in conflict: Atmos, NTMWD, City of Mesquite, and Oncor. Status of utilities in conflict is below. o AT&T: Clear o City of Crandall: Working on design for a few water line crossings in conflict. o Optimum: Design is complete. Awaiting pole relocations. o TVEC: Relocation plans are complete. Permits have been approved. Utility agreement has been executed. o Zayo: Permit has been approved. Pending construction. Kaufman County Transportation Report August 2026

Prepared by:

9


FM 741 at US 175

2019

CSJ:

1092-01-032

Schematic Approval:

*

Limits:

FM 741 at US 175 bridge

Environmental Clearance:

*

Project Description:

*

ROW Acquisition Complete:

*

Estimated Construction Cost:

$9,631,143

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Commissioner:

Tommy Moore, Precinct 4

Ready to Let Date:

*

Engineer & Key Contact:

HDR, Greg Kochersperger

Let Date:

*

TxDOT Project Manager:

Alex Borgan

Construction Start:

*

Current Activity: •

PS&E: HDR has refined conceptual design developed during proposal. HDR has developed a 15% geometric design for discussion with TxDOT. Kick-off meeting with TxDOT scheduled for August 31, 2026. Geotechnical team to perform test hole borings in September 2026.

Kaufman County Transportation Report August 2026

Prepared by:

10


Helms Trail

2019

CSJ:

*

Schematic Approval:

*

Limits:

from IH 20 to US 80

Environmental Clearance:

*

Project Description:

widen from 2-lane rural to 4-lane divided urban

ROW Acquisition Complete:

*

Estimated Construction Cost:

$38,250,000

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Commissioner:

Terry Crow, Precinct 1

Ready to Let Date:

*

Engineer & Key Contact:

Gannett Fleming, Donald Stephanik

Let Date:

*

TxDOT Project Manager:

*

Construction Start:

*

Current Activity: • •

Design: The 95% schematic submitted to ITS for review on November 11, 2025. Final schematic submittal, review, and approval will follow once construction funding can be identified for the project. Environmental: Environmental efforts paused pending identification of construction funding.

Kaufman County Transportation Report August 2026

Prepared by:

11


SH 205 South

TxDOT

CSJ:

0451-02-028

Schematic Approval:

July 3, 2018

Limits:

From US 80 to Kaufman County Line

Environmental Approval: Environmental Re-eval:

April 12, 2019 December 22, 2021

Project Description:

Widen from 2-lane rural to 4-lane urban divided with allowance for ultimate 6 lanes

ROW Acquisition Completed:

July 2023

Estimated construction cost:

$125,642,776

Utility Relocations Complete:

March 2028

Construction Funding:

$125,642,776 CAT 4

100% Plans:

August 2024

Engineer:

TxDOT

Ready to Let Date:

March 2028

TxDOT Contact:

Suja Mathew

Let Date:

*

Current Activity: • Utilities: Utilities that are clear of construction: Atmos, Dallas Water Utilities, High Point WSC, NTMWD, and Sprint. • Status of in conflict: o AT&T: Anticipate placement to be complete in September 2026. Splicing to follow. o FEC: Relocations complete; removal of poles to follow. o High Point WSC: Clear o Oncor: Relocations complete; pending removals. o Optimum: Relocations underway. Anticipate clearance in September 2026. o Terrell: Anticipate bidding of relocations in August 2026, and completion in May 2028. o Zayo: Plans approved. Pending relocations.

Kaufman County Transportation Report August 2026

Prepared by:

12


I-20 Frontage Roads – Terrell

TxDOT

CSJ:

0095-14-035; 0495-01-071

Schematic Approval:

January 31, 2019

Limits:

From CR 305 to SH 34

Environmental Approval:

April 10, 2020

Project Description:

Add continuous frontage roads

ROW Acquisition Completed:

October 2023

Estimated Construction Cost:

$382,746,499

Utility Relocations Complete:

December 2027

Construction Funding:

$0

100% Plans:

September 2025

Engineer & Key Contact:

LTRA

Ready to Let Date:

December 2027

TxDOT Project Manager:

Marlena Kelly

Let Date:

Pending Funding

Current Activity: •

Utilities: Utility coordination meetings are underway. Status of utilities in conflict below: o AT&T: Design approved for a crossing near The Shops at Terrell. Continuing to work on placement. o Atmos: Working on redesign due to The Shops at Terrell not allowing them to access property. o Enterprise: Clear o Oncor: Working to prepare relocations plans. o Oneok: Determined to be not in conflict. o Optimum: Pending relocations. o Rose Hill SUD: Working on 90% design. Utility agreement pending. o City of Terrell: Awaiting funding. o TVEC: Working to acquire easements. o Zayo: Preliminary plans sent to TxDOT on 8-14-26. TxDOT returned revisions on 8-25-26.

Kaufman County Transportation Report August 2026

Prepared by:

13


I-20 Frontage Roads – Kaufman

TxDOT

CSJ:

0095-14-036

Schematic Approval:

January 31, 2019

Limits:

From west of FM 741 to Big Brushy Creek

Environmental Approval:

April 10, 2020

Project Description:

Add continuous frontage roads

ROW Acquisition Complete:

December 2024

Estimated construction cost:

$189,612,460

Utility Relocations Complete:

December 2027

Construction Funding:

$0

100% Plans:

September 2026

Engineer & Key Contact:

WSB

Ready to Let Date:

December 2027

TxDOT Project Manager:

Gutema Gebriel

Let Date:

Pending Funding

Current Activity: • •

PS&E: WSB is working toward completion of the 100% plan set. Utilities: Utilities that are clear of construction: OneOK. Status of utilities in conflict below: o AT&T: Working on utility agreement and relocation plans. o NTMWD: Submitted 90% relocation plans for review. Utility agreement under review. o Oncor: Working on relocation plans. o Talty SUD: Working on relocation plans. o TVEC: Working on relocation plans. Working to obtain easements. o 4-in-one joint-venture water line (Crandall, College Mound, Gastonia-Scurry, Rose Hill): Determined not to be in conflict.

Kaufman County Transportation Report August 2026

Prepared by:

14


US 80 Widening

TxDOT

CSJ:

0095-03-080; -085

Schematic Approval:

August 24, 2018

Limits:

From Lawson Road to FM 460

Environmental Approval:

April 13, 2020

Project Description:

Reconstruct and widen from 4 to 6 main lanes and reconstruct 2/4-lane discontinuous to 4/6-lane continuous frontage roads

ROW Acquisition Completed:

February 2022

Estimated Construction Cost:

$128,902,801

Utility Relocations Complete:

June 2023

100% Plans:

March 2022

Construction Funding:

$146,274,571

$139,443,588: CAT 4; $1,882,263: CAT 6 $3,944,904: CAT 10; $1,003,816: CAT 11

Engineer & Key Contact:

Halff Associates, Jeremy McGahan

Let Date:

June 29, 2022

TxDOT Project Manager:

Cody Jolley

Construction Completion:

September 2026

Current Activity: •

Construction: The project let on June 29, 2022. The project was awarded to Webber, LLC, with a low bid of $128,902,801.08, at 7.40% above engineer’s estimate. There are 42 months of barricades and 1,086 working days. See attached TxDOT construction report.

Kaufman County Transportation Report August 2026

Prepared by:

15


TxDOT Monthly Project Report for Kaufman County Date of report: August 17, 2026 Report prepared by: Cody Jolley

Control: 0095-03-080 Limits Lawson Road to FM 460 Project: F 2022(793) Highway: US 80 Contractor: Webber, LLC TxDOT Project Manager: Chris Bruner Contractor’s Superintendent: Casey Tanner Contractor’s Superintendent: Robert Cox

Phone: (972) 962-3617 Phone: (281) 907-8600 Phone: (281) 907-8600

Date Work Began: April 4, 2023 Anticipated Completion Date: September 30, 2026

Current activities: Asphalt paving. Seeding/Sod. Sign installation. Painting. Punch list. Narrative description of last month’s activities: Asphalt paving. Removals. Excavation/Embankment. Seeding/Sod. Sign installation. Painting. Narrative description of activities planned for next month: Asphalt paving. Painting. Punch list. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report August 2026

Prepared by:

16


US 80/Spur 557 (FM 460 to IH 20)

TxDOT

CSJ:

0095-03-106; 0095-04-076; 0495-01-081

Schematic Approval:

December 2023

Limits:

From FM 460 to IH 20

Environmental Approval:

April 3, 2024

Project Description:

Widen and add lanes

ROW Acquisition Complete:

*

Estimated Construction Cost:

$1,196,508,338

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Engineer & Key Contact:

*

Ready to Let:

*

TxDOT Project Manager:

Grace Lo

Let Date:

*

Current Activity: •

PS&E: Awaiting TxDOT determination of priorities and next steps to advance project to PS&E phase.

Kaufman County Transportation Report August 2026

Prepared by:

17


Outer Loop

2019

CSJ:

0918-11-109

Schematic Approval:

September 2026

Limits:

From SH 205 to FM 148

Environmental Approval:

September 2026

Project Description:

4-lane freeway with continuous 4- to 6-lane frontage roads

ROW Acquisition Complete:

*

Estimated Construction Cost:

$2,326,099,280

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Engineer & Key Contact:

HDR, Brian Swindell

Ready to Let Date:

*

TxDOT Project Manager:

Liang Ding

Let Date:

*

Current Activity: • • • • • • • •

Design: HDR continues coordination with project stakeholders. HDR also continues coordination with TxDOT, Halff Associates (Rockwall County Outer Loop project), NCTCOG, and ITS. HDR is finalizing the schematic. HDR submitted draft ICE analysis and report. HDR continued work on draft IAJR documentation. Bi-weekly coordination meetings underway. Environmental: Public Hearing was held on June 30, 2026. Public comment period ended on July 30, 2026. There were 11 comments received, with comments generally supportive of the project. Public Hearing summary is in progress. ROW: ROW footprint approved on September 29, 2025. Other: Project website is available at: https://kaufmanouterloop.com.

Kaufman County Transportation Report August 2026

Prepared by:

18


FM 740/FM 460 CSJ:

2249-01-009; 1091-01-023

Limits: Project Description:

from Kaufman/Rockwall County Line to Ranch Road reconstruct FM 460 and FM 740 to 4lane (6-lane ultimate) divided urban roadways

2019

Schematic Approval:

November 12, 2025

Environmental Approval:

November 2026

ROW Acquisition Complete:

*

Estimated Construction Cost:

$135,806,715

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Commissioner:

Skeet Phillips, Precinct 2

Ready to Let Date:

*

Engineer & Key Contact:

Atkins, Thomas Le

Let Date:

*

TxDOT Project Manager:

Liang Ding

Construction Start:

*

Current Activity:

•

•

Environmental: TxDOT approved reclassification to CE from EA; this reclassification will save efforts and resources. Atkins continues efforts on environmental technical reports. Public Hearing has been scheduled for October 8, 2026, from 6:00 to 8:00 p.m. at Rhodes Intermediate High School, 775 Innovation Boulevard, Forney, TX 75126. Coordination meetings with Atkins, TxDOT, and ITS are ongoing.

Kaufman County Transportation Report August 2026

Prepared by:

19


US 175 Grade Separations – Kemp

2019

CSJ:

0197-05-063

Schematic Approval:

November 2023

Limits:

from Business US 175 to FM 1895

Environmental Approval:

November 26, 2024

Project Description:

construct grade separations of US 175 over BUS 175 and FM 1895

ROW Acquisition Complete:

NA

Estimated Construction Cost:

$94,294,483

Utility Relocations Complete:

September 2028

Construction Funding:

$0

100% Plans:

September 2027

Commissioner:

Tommy Moore, Precinct 4

Ready to Let Date:

September 2028

Engineer & Key Contact:

Halff, Melanie Cleavelin

Let Date:

*

TxDOT Project Manager:

Marlena Kelly

Construction Start:

*

Current Activity: •

•

PS&E: Halff submitted the 30% plan set on June 26, 2026. Halff Associates is addressing 30% plan comments and is working toward completion of 60% design, expected in September 2026. Utilities: Halff held first utility coordination meeting on August 4, 2026. Halff to coordinate with utilities for conflict analysis.

Kaufman County Transportation Report August 2026

Prepared by:

20


US 175 Feasibility Study CSJ/Project ID: Limits:

Project Description:

A00190822 From west of FM 1389 (Kaufman County line) to east of SH 198 (Henderson County line) Feasibility study to investigate capacity improvements including main lanes expansion and addition of continuous frontage roads and new interchanges

TxDOT

Schematic Approval:

*

Environmental Approval:

*

ROW Acquisition Complete:

*

Estimated Construction Cost:

*

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Engineer & Key Contact:

BGE, Hossein Hosseiny

Ready to Let Date:

*

TxDOT Project Manager:

Stephen Endres

Let Date:

*

Current Activity: • • •

Design: BGE continued developing design with an urban typical section throughout the county to minimize ROW impacts. BGE continued analyzing an urban section for the corridor and comparing impacts. TxDOT notified BGE to pause efforts effective February 11, 2025.

Kaufman County Transportation Report August 2026

Prepared by:

21


FM 148 CSJ:

0751-01-053

Limits: Project Description:

From US 175 to Country Woods Road (CR 261) Reconstruct and widen from 2 to 4 (6 ultimate) lanes

2019 Schematic Approval:

October 2027

Environmental Approval:

July 2028

ROW Acquisition Complete:

*

Construction Cost:

$84,775,625

Utility Relocations Complete:

*

Construction Funding:

$0

100% Plans:

*

Commissioner:

Terry Crow, Precinct 1

Let Date:

*

Engineer & Key Contact:

Westwood, Nelson Underwood

Construction Start:

*

TxDOT Project Manager:

Tamanna Ali

Construction Completion:

*

Current Activity: •

•

Design: Design Concept Conference was held on August 6, 2025. Additional discussion regarding potential for a new FM 148 at location of the new underpass required. Design work on hold until decision regarding alignment TxDOT would like to pursue is made. ITS is coordinating with the developer of the Cartwright Ranch. Westwood submitted revised options of immediate action improvements to existing FM 148 in July 2026. Revised options include extended two-way left-turn lane, right-turn lanes, and adjusted pavement widths. ITS is working to schedule a meeting with TxDOT, City of Crandall, and the developer to determine the preferred option. Survey: Aerial flight is complete and has being processed. Field work has been completed.

Kaufman County Transportation Report August 2026

Prepared by:

22


US 80

TxDOT

CSJ:

0095-03-100

Schematic Approval:

*

Limits:

From FM 460 to east of Buffalo Creek bridges

Environmental Approval:

August 30, 2023

Project Description:

Widen and replace eight bridges

ROW Acquisition Complete:

NA

Construction Estimate:

$98,459,064

Utility Relocations Complete:

January 2025

100% Plans:

January 2025

$98,459,060 Construction Funding:

CAT 4: $62,080,189 CAT 5: $978,871 CAT 6: $35,400,000

Commissioner:

Skeet Phillips, Precinct 2

Let Date:

October 2026

Engineer & Key Contact:

TxDOT, Morgan Neill

Construction Start:

*

TxDOT Project Manager:

Amir Shammet

Construction Completion:

*

Current Activity: •

Construction: Project is scheduled for letting in October 2026.

Kaufman County Transportation Report August 2026

Prepared by:

23


SH 198

TxDOT

CSJ/Project ID:

0443-02-023

Schematic Approval:

*

Limits:

From US 175 to FM 3080

Environmental Approval:

April 10, 2024

Project Description:

Widen roadway to add 2-way left-turn lane

ROW Acquisition Complete:

NA

Construction Cost:

$5,180,451

Utility Relocations Complete:

NA

Construction Funding:

$4,926,222

100% Plans:

July 2025

Engineer & Key Contact:

Jacobs, Abe Bekele

Let Date:

August 7, 2025

TxDOT Project Manager:

Falon Renfroe

Construction Completion:

November 2026

Current Activity: •

Construction: Project was awarded to A.L. Helmcamp, Inc. with a low bid of $5,180,451, at 5.4% above the engineer’s estimate. See attached TxDOT construction report.

Kaufman County Transportation Report August 2026

Prepared by:

24


TxDOT Monthly Project Report for Kaufman County Date of report: August 17, 2026 Report prepared by: Cody Jolley Control: 0443-02-023 Project: STP 2025(969) HES Highway: SH 198 Contractor: A. L. Helmcamp, Inc.

Limits: N. of US 175 to FM 3080

TxDOT Project Manager: Charlie Neal Contractor’s Superintendent: Marc Barahona

Phone: (972) 962-3617 Phone: (903) 626-5911

Date Work Began: November 10, 2025 Anticipated Completion Date: November 2026

Current activities: Subgrade widening. Placing flexbase. Driveway construction. Narrative description of last month’s activities: Subgrade widening. Driveway construction. Narrative description of activities planned for next month: Placing flexbase. Asphalt. Driveway construction. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report August 2026

Prepared by:

25


SH 243 Safety Improvements

TxDOT

CSJ/Project ID:

0522-01-026

Schematic Approval:

*

Limits:

From SH 34 to FM 2727

Environmental Approval:

April 10, 2024

Project Description:

Add continuous left-tun lane on SH 243

ROW Acquisition Complete:

NA

Construction Cost:

$3,537,961

Utility Relocations Complete:

NA

Construction Funding:

*

100% Plans:

June 2025

Engineer & Key Contact:

Jacobs, Abe Bekele

Let Date:

August 8, 2025

TxDOT Project Manager:

*

Construction Completion:

January 2027

Current Activity: •

Construction: Project was awarded to A.L. Helmcamp with a low bid of $3,537,961 at 2.5% under the engineer’s estimate. Pre-construction meeting was held on November 4, 2025. See attached TxDOT construction report.

Kaufman County Transportation Report August 2026

Prepared by:

26


TxDOT Monthly Project Report for Kaufman County Date of report: August 17, 2026 Report prepared by: Cody Jolley Control: 0522-01-026 Project: STP 2025(970) HES Highway: SH 243 Contractor: A. L. Helmcamp, Inc.

Limits: SH 34 to FM 2727

TxDOT Project Manager: Jacob Self Contractor’s Superintendent: Jason Keeling

Phone: (972) 962-3617 Phone: (903) 626-5911

Date Work Began: November 10, 2025 Anticipated Completion Date: January 2027

Current activities: Driveway construction. Narrative description of last month’s activities: Drainage installations. Narrative description of activities planned for next month: Subgrade widening. Driveway construction. Traffic issues: None Plans for changes in traffic patterns: None Item(s) of work currently controlling project completion: None Other items of significance: None

Kaufman County Transportation Report August 2026

Prepared by:

27


Glossary of Acronyms • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • • •

•

AADT – Annual Average Daily Traffic AFA – Advanced Funding Agreement ARPA – Archeological Resources Protection Act ASED – Annual Scope & Estimate Documentation CE – Categorical Exclusion (environmental clearance process for projects that do not involve significant environmental impacts) CLOMR – (FEMA’s) Conditional Letter of Map Revision Conformity – Federal requirement in nonattainment areas to conduct air quality analysis on projects, programs, and policies identified in transportation plans, transportation improvement programs, federally funded projects, or projects requiring federal approval CSJ – (TxDOT’s) Control Section Job Number EA – Environmental Assessment ED – Eminent Domain EIS – Environmental Impact Statement EPIC – Environmental Permits, Issues, and Commitments FONSI – Finding of No Significant Impact IAJR – Interstate Access Justification Request ICA – Interlocal Cooperative Agreement IFP – Initial Financial Plan LOSA – Local On-system Agreement MAPO – Meeting with Affected Property Owners MPO – Metropolitan Planning Organization MTP – Metropolitan Transportation Plan NCTCOG – North Central Texas Council of Governments NEPA – National Environmental Policy Act NOPC – Notice of Proposed Construction NORA – Notice of Required Accommodation NTTA – North Texas Toll Authority PBLR – Preliminary Bridge Layout Review PS&E – Plans Specifications and Estimate PUA – Possession and Use Agreement ROW – Right-of-Way RTC – Regional Transportation Council RTL – Read to Let (date project is clear for construction but lacks funding for actual let) RTR – Regional Toll Revenue (funds resulting from certain toll/managed lane projects in DFW region) RULIS – Right-of-Way, Utilities, Leasing, and Information System STBG – Surface Transportation Block Grant STIP – Statewide Transportation Improvement Program SUE – Subsurface Utility Engineering SW3P – Storm Water Pollution Prevention Plan TIA – Time Impact Analysis TPP – Transportation Planning and Programming TPWD – Texas Parks & Wildlife Department TTC – Texas Transportation Commission TxDOT – Texas Department of Transportation UTP – Unified Transportation Program VE – Value Engineering

Kaufman County Transportation Report August 2026

Prepared by:

28


TxDOT Funding Categories • • • • • • • • • • • •

CAT 1: Preventive Maintenance and Rehabilitation CAT 2: Metropolitan and Urban Area Corridor Projects / RTC CAT 3: Non-Traditionally Funded Transportation Projects CAT 4: Statewide Connectivity Corridor Projects CAT 5: Congestion Mitigation and Air Quality Improvement / RTC CAT 6: Structures Replacement and Rehabilitation (Bridge) CAT 7: Metropolitan Mobility and Rehabilitation / RTC CAT 8: Safety Projects CAT 9: Transportation Alternatives CAT 10: Supplemental Transportation Projects CAT 11: District Discretionary CAT 12: Strategic Priority

Kaufman County Transportation Report August 2026

Prepared by:

29