City Manager’s

Quarterly Report To: Mayor and City Council From: Robert Ranc, City Manager

AUGUST 14, 2026


SECTION 1 OBJECTIVES & KEY RESULTS


SECTION 2 FINANCIAL SUMMARY


GENERAL FUND Revenues General Fund revenues total $59,244,847 through June 30, 2026. This represents an increase of 3.7% from revenue earned in the preceding year. Ad valorem taxes represent 19% of the current increase and due to the timing they are at 99.29% collections for the fiscal year. Permits represents -16% of the current increase, are the second largest source of funds, and is currently tracking on target with the budget. The city has recognized a reduction in single family building permits. However conversely the commercial permit activity has offset the reduction. The table below provides a summary of total General Fund revenues as of June 30th:

PROPERTY TAX SALES TAX OTHER TAXES PERMITS & LICENSES FINES & FEES INTEREST GRANTS CONTRIBUTIONS/DONATIONS OTHER REVENUE TRANSFERS IN Totals

$

$

2025-2026 Activity

Percent of Total

28,522,468 3,646,237 1,384,469 18,923,613 3,611,643 1,471,631 195,698 284,562 1,204,525 59,244,847

48.1% 6.2% 2.3% 31.9% 6.1% 2.5% 0.3% 0.5% 2.0% 0.0% 100.0%

The table below provides a comparison between FY 2025 and FY 2026 Activity: 2025-2026 Activity PROPERTY TAX SALES TAX OTHER TAXES PERMITS & LICENSES FINES & FEES INTEREST GRANTS CONTRIBUTIONS/DONATIONS OTHER REVENUE TRANSFERS IN Totals

$

$

28,522,468 3,646,237 1,384,469 18,923,613 3,611,643 1,471,631 195,698 284,562 1,204,525 59,244,847

2024-2025 Activity $

$

23,951,070 3,162,195 1,027,425 22,523,307 2,802,918 1,577,255 440,236 334,895 1,303,255 57,122,555

$

$

Increase/Decrease

Percent Change

4,571,398 484,043 357,044 (3,599,695) 808,726 (105,624) (244,538) (50,333) (98,730) 2,122,291

19.1% 15.3% 34.8% -16.0% 28.9% -6.7% 0.0% -15.0% -7.6% 0.0% 3.7%


GENERAL FUND Expenditures Expenditures for General Fund were $45,571,656 through June 30, 2026. This is an increase of $10,071,511 or 28.4%. The expenditures have increased due to new positions and services provided to meet the demands of the growing City unless noted below.

Department CITY MANAGER'S OFFICE* CITY SECRETARY'S OFFICE FINANCE HUMAN RESOURCES INFORMATION TECHNOLOGY MUNICIPAL COURT FACILITIES MAINTENANCE STRATEGIC SERVICES* NON-DEPARTMENTAL General Government GIS BUILDING SERVICES* PLANNING* CODE SERVICES* ENGINEERING Development & Engineering LIBRARY MARKETING PARKS Culture & Recreation FIRE/EMS POLICE Public Safety STREETS Public Services Total Expenditures

2025-2026 2024-2025 Activity Activity $ 855,042 $ 825,042 276,758 211,591 1,686,279 1,474,235 824,511 793,918 2,611,245 1,891,927 249,878 225,770 424,829 286,922 554,641 338,479 5,124,173 1,445,393 $ 12,607,355 $ 7,493,276 419,741 365,982 1,870,832 1,888,672 903,598 747,802 329,528 244,618 2,439,320 1,988,012 $ 5,963,019 $ 5,235,086 495,182 318,121 2,016,282 1,790,035 2,051,092 1,993,493 $ 4,562,555 $ 4,101,648 9,824,229 8,496,713 10,341,936 8,657,971 $ 20,166,164 $ 17,154,684 2,272,563 1,515,451 $ 2,272,563 $ 1,515,451 $ 45,571,656 $ 35,500,145

$

$

$

$

$ $ $

Increase/ Decrease 30,000 65,167 212,045 30,592 719,317 24,108 137,907 216,162 3,678,780 5,114,078 53,759 (17,839) 155,796 84,910 451,308 727,933 177,061 226,247 57,599 460,907 1,327,516 1,683,965 3,011,481 757,112 757,112 10,071,511

Percent Change Material Variance Drivers 3.6% 30.8% Position vacancy during FY 2025. 14.4% 3.9% 38.0% Added 3 full time positions in FY 2026 10.7% 48.1% Added a Facility Technician Position in FY 2026. 63.9% Strategic Services personnel vacancies have been filled 254.5% Utilities, insurance, transfers, and grant expense. 68.2% 14.7% -0.9% Residential building permits and inspections slowed. 20.8% Added a Development Coordinator Position in FY 2026. 34.7% Added a Rental Inspector Position in FY 2026. 22.7% 13.9% 55.7% Library Director was vacant to begin FY 2025. 12.6% Increased festival funding and quantity. 2.9% 11.2% 15.6% Added positions and equipment to keep up with growth. 19.4% Added positions and equipment to keep up with growth. 17.6% 50.0% Added Streets Crew and one time equipment. 50.0% 28.4%

Expenditures by Function General Government

$

12,607,355

27.7%

5,963,019

13.1%

Culture & Recreation

4,562,555

10.0%

Public Safety

20,166,164

44.3%

Public Services

2,272,563

5.0%

45,571,656

100.0%

Development & Engineering

Total

$

*During FY 2025 the Administration Department was split into the City Manager's Office and Strategic Services Department, the Development Services Department was split into the Building Services, Planning, and Code Services Divisions, and a nondepartmental division was added.


Water & Wastewater Fund Revenues Operating revenues for the Water & Wastewater Fund through June 30, 2026 were $39,650,863, which is a decrease of $435,601 or 1.1%. The decrease is due to less new utility accounts added to the system resulting in a decrease of Water and Wastewater Connection Fees from FY 2025 to 2026 of $1,978,400.

The table below provides a summary of total Water/Wastewater revenues as of June 30th: 2025-2026 Activity CHARGES FOR SERVICES FINES & FEES INTEREST OTHER REVENUE TRANSFERS IN Totals

$

$

30,219,859 6,007,714 1,529,736 1,893,554 39,650,863

2024-2025 Activity $

$

28,339,298 7,986,114 1,485,401 2,275,652 40,086,464

$

$

Increase/Decrease

Percent Change

1,880,562 (1,978,400) 44,335 (382,099) (435,601)

6.6% -24.8% 3.0% -16.8% 0.0% -1.1%

Increase/Decrease

Percent Change

569,383 1,311,179 1,880,562

3.5% 11.0% 6.6%

The table below provides a breakdown of Charges for Services: 2025-2026 Activity WATER SALES WASTEWATER SALES Totals

$ $

17,005,523 13,214,336 30,219,859

2024-2025 Activity $ $

16,436,140 11,903,157 28,339,298

$ $


Water/Wastewater Fund Expenditures Water and Wastewater expenditures through June 30, 2026 are $25,044,413 which is $6,189,561 or 32.8% more than FY 2025. The increase in expenditures is due to heightened service requirements from increased customer counts and expansions to the utility system funded through capital purchases and debt payments.

The table below provides a comparison of expenditures in FY 2025 and FY 2026: 2025-2026 Activity PAYROLL LEGAL & PROFESSIONAL MATERIALS & SUPPLIES MAINTENANCE EXPENSE UTILITY EXPENSE MISCELLANEOUS EXPENSE CAPITAL DEBT COST OF SERVICES (UTRWD WATER) TRANSFERS OUT CAPITAL IMPROVEMENT PROJECTS Totals

$

$

3,154,028 486,199 1,911,931 324,755 517,204 1,644,099 422,197 8,538,318 8,045,684 25,044,413

2024-2025 Activity $

$

2,364,680 400,739 1,413,002 237,942 476,674 1,301,781 520,241 5,595,151 6,544,642 18,854,852

$

$

Increase/Decrease

Percent Change

789,348 85,459 498,929 86,813 40,529 342,318 (98,044) 2,943,167 1,501,042 6,189,561

33.4% 21.3% 35.3% 36.5% 8.5% 26.3% -18.8% 52.6% 22.9% 0.0% 0.0% 32.8%


3rd Quarter 2026

General Fund - Schedule of Revenues Budget vs. Actuals

Account Name

2024-2025 Activity

SALES TAX $ PROPERTY TAX-CURRENT CONTRA - PROPERTY TAX PROPERTY TAX-DELINQUENT CONTRA - SALES TAX FRANCHISE TAXES - ELECTRICITY FRANCHISE TAXES - GAS FRANCHISE TAXES - TELEPHONE FRANCHISE TAXES - CABLE TV MIXED BEVERAGE TAX TAXES Totals: $

3,323,904 23,784,499 (73,024) 239,595 (161,709) 480,412 511,911 4,160 7,059 23,883 28,140,689

PERMITS DEVELOPMENT FEES CONSTRUCTION INSPECTION FEES ISD PERMIT FEES PROFESSIONAL STUDY FEES PERMITS & LICENSES Totals:

$

17,889,996 192,122 4,354,852 86,338 22,523,307

FINES & FEES Totals: $

$

2025-2026 Original Budget

$

$ $

6,736,860 27,895,669 (3,387,120) 160,370 (511,875) 975,000 600,000 10,000 22,000 60,000 32,560,904

Percent of Year Expired 2025-2026 Revised Budget

$

$ $

2025-2026 Activity

6,736,860 27,895,669 (3,387,120) 160,370 (511,875) 975,000 600,000 10,000 22,000 60,000 32,560,904

$

$

Percent Budget Collected

Percent Budget Collected Prior Year

(2,097,689) (27,897,629) 70,206 (154,755) 49,932 (292,594) (734,174) (1,707) (4,011) (26,421) (31,088,841)

31% 100% 2% 96% 10% 30% 122% 17% 18% 44% 95%

65% 100% 2% 178% 27% 62% 107% 55% 32% 101% 105%

81% 65% 84% 0% 48% 81%

110% 85% 121% 0% 35% 111%

2,097,689 27,897,629 (70,206) 154,755 (49,932) 292,594 734,174 1,707 4,011 26,421 31,088,841

$

$

$

13,928,822 129,512 3,230,649 185,329 17,474,312

$

(13,928,822) (129,512) (3,230,649) (185,329) (17,474,312)

$

$

75%

2025-2026 Budget Remaining

$

17,250,000 200,000 3,850,000 205,000 21,505,000

$

17,250,000 200,000 3,850,000 384,628 21,684,628

2,802,918

$

3,702,700

$

3,702,700

$

3,611,643

$

(3,611,643)

98%

86%

INTEREST Totals: $

1,577,255

$

1,575,000

$

1,575,000

$

1,471,631

$

(1,471,631)

93%

105%

GRANTS Totals:

$

440,236

$

517,000

$

620,390

$

195,698

$

(195,698)

32%

34%

CONTRIBUTIONS/DONATIONS Totals:

$

334,895

$

414,250

$

414,250

$

284,562

$

(284,562)

69%

73%

OTHER REVENUE Totals: $

1,303,255

$

1,687,244

$

1,742,433

$

1,204,525

$

(1,204,525)

69%

87%

TRANSFERS IN Totals:

$

-

$

1,473,692

$

1,473,692

$

-

$

-

0%

0%

REVENUE Totals:

$

57,122,555

$

63,435,790

$

63,773,997

$

55,331,213

$

(55,331,213)

87%

101%


3rd Quarter 2026 Department CITY MANAGER'S OFFICE CITY SECRETARY'S OFFICE FINANCE HUMAN RESOURCES INFORMATION TECHNOLOGY MUNICIPAL COURT FACILITIES MAINTENANCE STRATEGIC SERVICES NON-DEPARTMENTAL General Government GIS BUILDING SERVICES PLANNING CODE SERVICES ENGINEERING Development & Engineering LIBRARY MARKETING PARKS Culture & Recreation FIRE/EMS POLICE Public Safety STREETS Public Services Total Expenditures

General Fund - Schedule of Expenditures Budget vs. Actuals

2024-2025 Activity $ 825,042 211,591 1,474,235 793,918 1,891,927 225,770 286,922 338,479 1,445,393 $ 7,493,276 365,982 1,888,672 747,802 244,618 1,988,012 $ 5,235,086 318,121 1,790,035 1,993,493 $ 4,101,648 8,496,713 8,657,971 $ 17,154,684 1,515,451 $ 1,515,451 $ 35,500,145

2025-2026 Original Budget $ 1,517,079 408,357 2,446,242 1,187,574 3,388,800 354,847 716,252 844,432 7,382,314 $ 18,245,897 559,942 3,309,375 1,548,478 556,406 3,757,866 $ 9,732,067 902,026 2,631,663 3,501,252 $ 7,034,941 15,018,387 15,414,073 $ 30,432,460 3,661,259 $ 3,661,259 $ 69,106,624

2025-2026 Budget 2025-2026 Transfers Budget $ 130,590 $ 1,647,669 34,144 442,501 58,339 2,504,581 34,248 1,221,822 308,769 3,697,569 14,840 369,687 879 717,131 49,154 893,586 5,319,920 12,702,234 $ 5,950,883 $ 24,196,780 22,441 582,383 (985) 3,308,390 68,957 1,617,435 (2,987) 553,419 233,874 3,991,740 $ 321,300 $ 10,053,367 10,163 912,189 250,097 2,881,760 139,541 3,640,793 $ 399,801 $ 7,434,742 233,144 15,251,531 272,301 15,686,374 $ 505,445 $ 30,937,905 821,175 4,482,434 $ 821,175 $ 4,482,434 $ 7,998,604 $ 77,105,228

Percent of Year Expired

2025-2026 Encumbrance $ 8,022 9,136 112,065 44,288 213,761 1,579 119,199 31,859 43,183 $ 583,091 310 49,476 8,804 1,184 368,253 $ 428,027 37,490 60,179 277,301 $ 374,970 299,106 255,617 $ 554,723 893,423 $ 893,423 $ 2,834,233

2025-2026 Activity $ 855,042 276,758 1,686,279 824,511 2,611,245 249,878 424,829 554,641 5,124,173 $ 12,607,355 419,741 1,870,832 903,598 329,528 2,439,320 $ 5,963,019 495,182 2,016,282 2,051,092 $ 4,562,555 9,824,229 10,341,936 $ 20,166,164 2,272,563 $ 2,272,563 $ 45,571,656

2025-2026 Budget Remaining $ 784,606 156,607 706,237 353,023 872,564 118,231 173,104 307,086 7,534,878 $ 11,006,335 162,333 1,388,081 705,033 222,707 1,184,167 $ 3,662,321 379,517 805,299 1,312,400 $ 2,497,217 5,128,197 5,088,821 $ 10,217,018 1,316,448 $ 1,316,448 $ 28,699,339

Percent Budget Obligated Current Year 52% 65% 72% 71% 76% 68% 76% 66% 41% 55% 72% 58% 56% 60% 70% 64% 58% 72% 64% 66% 66% 68% 67% 71% 71% 63%

*During FY 2025 the Administration Department was split into the City Manager's Office and Strategic Services Department, the Development Services Department was split into the Building Services, Planning, and Code Services Divisions, and a non-departmental division was added. These changes were made to allow better tracking of expenses in the City.

75% Percent Budget Obligated Prior Year 30% 60% 10% 80% 78% 85% 27% 0% 0% 32% 87% 46% 0% 0% 69% 70% 50% 86% 67% 72% 78% 83% 80% 46% 46% 58%


3rd Quarter 2026

Water/Wastewater Fund - Schedule of Revenues Budget vs. Actuals

Account Name

2024-2025 Activity

2025-2026 Original Budget

RECONNECT/DISCONNECT FEES $ CUSTOMER SERVICE FEES TRANSFER FEES WATER CONNECTION FEES WASTEWATER CONNECTION FEES PENALTIES FINES & FEES Totals: $

45,300 3,882 1,450 4,624,275 3,105,300 205,906 7,986,114

$

INTEREST Totals: $ OTHER REVENUE Totals: $

$

36,000 8,000 1,400 5,820,000 2,800,000 240,000 8,905,400

2,040,000

$

$

2,478,000

$

16,436,140 11,903,157 28,339,298

TRANSFERS IN Totals: $

WATER SALES WASTEWATER SALES CHARGES FOR SERVICES Totals:

Revenue Totals:

WATER DEPARTMENT WASTEWATER COLLECTIONS*

$

$

36,000 8,000 1,400 5,820,000 2,800,000 240,000 8,905,400

1,485,401

$

2,275,652

Percent of Year Expired 2025-2026 Encumbrance

2025-2026 Revised Budget

2025-2026 Budget Remaining

$

75%

Percent Budget Collected/Expensed Current Year

Percent Budget Collected/Expensed Prior Year

$

9,750 (5,356) (50) 2,360,925 514,900 17,517 2,897,686

73% 167% 104% 59% 82% 93% 67%

181% 26% 104% 116% 111% 103% 113%

$

$

-

$

26,250 13,356 1,450 3,459,075 2,285,100 222,483 6,007,714

2,040,000

$

-

$

1,529,736

$

510,264

75%

68%

$

2,498,709

$

-

$

1,893,554

$

605,155

76%

124%

$

26,878,152 17,696,000 44,574,152

$

26,878,152 17,696,000 44,574,152

$

-

$

17,005,523 13,214,336 30,219,859

$

9,872,629 4,481,664 14,354,293

63% 75% 68%

76% 90% 81%

-

$

-

$

-

$

-

$

-

$

-

0%

0%

$

40,086,464

$

57,997,552

$

58,018,261

$

-

$

39,650,863

$

18,367,398

68%

79%

$

8,524,534 2,800,080

$

18,407,688 6,230,500

$

18,536,930 6,230,500

$

6,054,473 2,104,649

$

10,729,802 2,974,915

$

1,752,654 1,150,936

58% 48%

47%

WASTEWATER TREATMENT*

$

2025-2026 Activity

49%

496,452

1,681,251

1,685,418

237,650

996,157

451,611

59%

39%

UTILITY BILLING

1,089,881

1,801,372

1,803,216

16,878

1,262,099

524,238

70%

77%

DEBT SERVICE - CITY DEBT

4,189,565

16,599,087

16,599,087

-

5,882,436

10,716,651

35%

29%

DEBT SERVICE- UTRWD DEBT

1,754,340

4,798,503

4,798,503

1,599,500

3,199,003

-

67%

55%

-

10,517,146

10,517,146

-

-

10,517,146

0%

0%

25,113,236

42%

34%

NON-DEPARTMENTAL Expenditure Totals:

$

18,854,852

$

60,035,547

$

60,170,800

$

10,013,150

$

25,044,413

$

*During FY 2025 the Wastewater Department was split into the Wastewater Collections and Wastewater Treatment Divisions. These changes were made to allow better tracking of expenses in the City.


SECTION 3 CAPITAL IMPROVEMENTS PROJECTS


W PE W WALNUT ST

CAN ST

2025 Wastewater Downtown Improvements Project ID: W84

W MA

IN ST

Project Phase: Design Description:

O ST

Status:

A DR S LOU ISIAN

S COL ORAD O

Awaiting the 95% submittal. The project scope was expanded to meet LCRR requirements, with funds reallocated within the original work authorization to cover the additional work. OMA DR KLAH SO

S UTAH DR

Funding: 2025 Bond Funds, 2026 Bond Funds, 2027 Bond Funds, 2028 Bond Funds, 2029 Bond Funds

ST

S ALABAMA DR

W ASH ST

K ST S A RI Z ONA DR

W OA

Rehabilitation/Replacement of multiple segments of sanitary sewer lines in various locations around the downtown area.

ST

S OHI

TOLLESON DR

W ELM

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 1 of 69

Estimated Completion

Estimated Total Cost

December 2026

$1,957,000


Rd St

ton

SP

rest

on

Rd

Funding: 2025 Bond Funds, 2026 Bond Funds, 2027 Bond Funds, 2028 Bond Funds, 2029 Bond Funds Status:

StElm St E Elm E

Rd

E ASH ST

Awaiting the 95% submittal. The project scope was expanded to meet LCRR requirements, with funds reallocated within the original work authorization to cover the additional work.

S

S P P RE S res t o nTON R d RD

SP

E Ash

res

AN ST St E PEEC Peca n

St

rk a n

S A

k St

NP

N Texas St

Rehabilitation/Replacement of multiple segments of potable water in various locations around the downtown area.

on

a nsa s

s a s SS tA rk

S S B usines s 28 9 OKLAHOMA DR

W F M 42 8

Project Progress

n

Project Phase: Design Description:

St

a Dr lah om S Ok a Dr S Ok la h om

a Dr

o St

BLVD W SUNSET W Sun set Blvd

E Oa

ca

Project ID: W84

rest

i si a na

Dr

i s i a na S Lou

St

a k St

S Ohi

C o l o r DO S ado S T t

E Pe

in St

W Elm

S CSOLORA

TOLLESON DR

DR STEFHANIE Stefhanie Dr

Zion

Pk w

y

Ye llow stone D r

ch St

t

Olymp ic Dr

Project Status

le St

S Te xas St

W C e d a r St

S Uta h St

Way

W Ce dar S t

S A R IZ S Ari z o n a D r ONA DR

W ASH ST S Alabam a St

p r in g s

l nut S

O ak St

W Ash St

E Bee

isia n

WWOAK ST

z ona

Dr

W Ma

S Ari

W E

m St W ELlM ST

E Map

289C

S L ou

LABAMA DR SaA b am a St

W Wa

W MAIN ST

S Al

Stefhanie Dr

T o l l eson Dr

S Ken t ucky St

W Walnut St

W Elm St

t

E MALONE ST E Malo ne St

E Ma lone St

N Oh

W WALNUT ST

W O

tS Ho

ech S

t

io St

ST

W Be

ple S

N Lou

Dr

i z ona N Ar

noi s

N Illi

St W Pe c n S t

W FM 455

N OKLAH

D

N FLORIDA DR

N LOUr ISIAN A

DR

Sha de Tree L n

N Flor id a Dr

WP E a CAN

W Ma

R AD M O

2025 Water Downtown Improvements

289

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project 2 of 69

Estimated Completion

Estimated Total Cost

December 2026

$1,957,000


A DR

BODARK LN

N LOU ISIAN

ST N CO LORA DO CH ST

ZONA DR

W PEC AN ST

Status: Construction substantially complete. Final walk held and punchlist items being addressed. Final acceptance contingent to Government Building CIP project (B33). AHOM A DR A DR S LOU ISIAN

K ST

S OKL

S COL ORAD O

ST

O ST

IN ST ST

W OA

This project will fund the design and reconstruction of Arizona St from Pecan St to Walnut St with subsurface utilities and concrete pavement. Drainage, sign, lighting, landscaping, and pavement marking improvements will also be included in the project.

2024 Bond Funds, Road Capital Recovery

S OHI

S A RI Z ONA DR

S ALABAMA DR

W ELM

Description:

Funding:

W MA

W ASH ST

Project Status

Project Phase: Construction

N A RI

W WALNUT ST

PLE S T N OH IO ST

W BEE

Project ID: R86

N OK LAHO MA D R

DR N O IS N IL L I

N FLORIDA DR

W MA

Arizona Dr (Walnut to Pecan)

Project Progress

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project 3 of 69

Estimated Completion

Estimated Total Cost

December 2026

$830,000


E WA

ST

Ash St and Oklahoma St Intersection Improvement

IN ST

E MAI N ST

S NE W

ST

ST

Description:

S A RK ANSA AHOM A DR

A DR S LOU ISIAN

ST

ST

S COL ORAD O

E OAK

Design of approximately 350LF of Ash St from the eastern limit of the BNSF railroad track to Oklahoma to align lanes with the ultimate eastern leg of Ash currently under construction. The project will include widening of the intersection with asphalt, drainage, signage and pavement markings to guide drivers.

ST

E ASH

Funding:

ST

TBD Status:

EST ON R

D

Design is completed and will be constructed with 2026 Annual Street Maintenance.

S PR

ZONA DR

Project Phase: Design

S OKL

K ST

W ASH

S ARI

E ELM

S OHI

W OA

Project ID: R115

S ST

O ST

W ELM

MEXIC O

DR

W MA

LNUT

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 4 of 69

Estimated Completion

Estimated Total Cost

October 2026

$630,000


Celina Pkwy Schematic

Project ID: R50

FM 428

COUNTY ROAD 55

Project Phase: Design Description: Schematic design for Celina Pkwy from FM 428 to the Collin County Outer Loop. Funding: Roadway Impact (Zone 3)

S CELINA PKWY

Status:

EMMANUEL LN

City is to coordinate with impacted property owners and Atmos gas company on the proposed alignment.

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 5 of 69

Estimated Completion

Estimated Total Cost

TBD

$130,000


Celina Rd Ground Storage Tank #2

Project ID: W77 Project Phase: Design Description: This project includes the construction of an additional six million gallons per day ground storage tank at Celina Rd Pump Station. The proposed project will provide additional storage capacity to serve future growth in the low-pressure plane and high-pressure plane. The project will be completed in coordination with the 54” water line along Glendenning Pkwy from Celina Rd Pump Station to Dallas Pkwy, the increased pumping capacity at Celina Rd Pump Station, and the new Upper Trinity Regional Water District delivery point.

CELINA RD FM

42

8

Funding: 2027 Bond Funds, 2028 Bond Funds Status: 100% plans are completed.

Contact: Mina Zamanian 469-813-4095 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 6 of 69

Estimated Completion

Estimated Total Cost

TBD

$15,575,000


Celina Rd Well and SE Pump Station Well

N PRES TON RD

N DALLAS PKWY COUNTY ROAD 9

COUNTY ROAD 57

N LOUISIANA DR

W J FRED SMITH PKWY

LYNN STAMBAUGH PKWY

Project ID: W80 Project Phase: Design

COUNTY ROAD 8

S OKLAHOMA DR

W FM 455

Design and construction of 2 Wells within the City of Celina. E SUNSET BLVD

Funding: 2025 Bond Funds, 2026 Bond Funds, 2027 Bond Funds

Project Status

LIGHT FARMS WAY

COUNTY ROAD 50

MCNAB B DR

W

NK PU

WY PK R E RT CA

S LEGACY DR

P W OUTER LOO

Project Progress

E OUTER

LOOP

S COIT RD

Status: S PRESTON RD

HUDDLESTON DR

S DALLAS PKWY

FM 428

FM 428 W

Description:

Celina Road Well is under consturction and progressing based on schedule. The Design of the SE Pump Station Well is finished, construction is slated for FY2027.

CHOATE PKWY

PUNK CARTER PKWY

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project 7 of 69

Estimated Completion

Estimated Total Cost

January 2028

$16,550,000


Choate Pkwy – Coit Rd to Roseland Pkwy

OLD GLENDENNING RD

RO SE LA N D

F M 2 478

PK W Y

Project ID: R66 Project Phase: Construction Description: This project consists of the reconstruction of the existing road as a two-lane divided primary arterial within the ultimate right-of-way of a six-lane divided arterial. Drainage, signage, and pavement markings will be included in the project. Lighting and landscaping will not be included in the project. This project will be a shared project between the City and the adjacent subdivision developer.

E OUTER LOOP AM

ST

HARDWOOD DR

FM 247

S COIT RD

R RI

FM 24 7 8

ME

CHOATE PKWY

8

KINSHIP PKWY

2023 Bond Funds, 2024 Bond Funds Status: The project is divided into two phases. The 1st phase approximatly 0.55 mile from Coit Rd is under construction. The 2nd phase is delayed due to Utility relocation. The anticipated construction start date is Fall 2026.

PUNK CARTER PKWY

AZURE LN

EO W NS BY PK W Y

Project Status

Project Progress

N Cust er Rd

PALOMINO LN

OLD STABLES DR

Funding:

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

Project 8 of 69

Estimated Completion

Estimated Total Cost

May 2027

$10,910,000


Project ID: R118 Project Phase: Design Description: Signing and striping plans for a school zone at a new Junior High School.

AY W

Funding:

COUNTY ROAD 101

Road Capital Recovery Fund Status:

TREELIN E LN

Awaiting the material estimate and fund allocation for material procurement.

TRAILHEAD DR

N COIT RD

R

DR

E BL M A

MYRTLE DR

E HIK DAY

PRAIRIE MEADOW LN

CISD Janet H. Calvert Elementary School Zone

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 9 of 69

Estimated Completion

Estimated Total Cost

TBD

TBD


BEEBALM MEWS

VANILLA BIRCH LN

DR

Project ID: R105 BEAR GRAS SM EW S

BLE WIL L

HYS SOP DR

NI M

CISD Willard Middle School Zone

Project Phase: Construction Description:

BLUE SAGE CT

OLD GLENDE NNING RD VETIVER GLOW DR

Signing and striping plans for a school zone at the new Willard Middle School located at the southwest corner of Coit Rd and Old Glendenning Rd. Funding: Road Capital Recovery Fund Status:

IUM LN

CHICORY LN

G E R AN

S COIT RD

Construction will be complete before school opens in Fall 2026.

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project Status

Project Progress

Project 10 of 69

Estimated Completion

Estimated Total Cost

August 2026

$12,000


Coit Rd - 1400' North of Frontier Pkwy

MA R IGOL D L N

Project ID: R70 Project Phase: Design

This project consists of the expansion of the existing two-lane roadway to a four-lane primary arterial divided within the ultimate right-of-way of a six-lane divided arterial. Drainage, signage, and pavement markings will be included in the project. Lighting and landscaping will not be included in the project. This project will be completed in conjunction with the Town of Prosper and the construction of Coit Rd from Frontier Pkwy south within the Town of Prosper.

S COIT RD

FALCON RD

TWIN LAKES DR

Description:

Funding: 2023 Bond Funds Status: Plans will be added to Prosper's Coit (south of Frontier) plans for construction. Plans are almost completed. There is an ILA between City of Celina and Town of Prosper for Prosper to undertake the construction of road. Plans are being revised to include the relocation of traffic signal at Frontier and Coit intersection. Coordination with TxDOT is also ongoing. There are no identified conflicts with franchise utilities in Celina's section. Construction is tentatively scheduled for Fall 2026

E FRONTIER PKWY

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 11 of 69

Estimated Completion

Estimated Total Cost

July 2027

$1,750,000


E OUT ER LO OP

Coit Rd Improvements (Vest Ln to Choate Pkwy)

MERRIAM ST

HARDWOOD DR

Project ID: R57

CHOATE PKWY

Project Phase: Construction KIN SHI

P PK

Description:

PALOMINO LN

HARKAWAY CT

LANDMARK DR

EVERGREEN TRL

BERRY ST

S COIT RD

OLD STABLES DR

WY BLUEBIRD WAY

PUNK CARTER PKWY

LAWNDALE ST AZURE LN

This project will include the reconstruction of the existing two-lane asphalt road into a four-lane divided primary arterial within the ultimate ROW of a six-lane divided arterial. This project will include right-of-way acquisition, drainage, roundabouts, and sign and pavement markings. Lighting and landscaping will included as well. This project will be a shared project between the City and Collin County. Funding: 2022 Bond Funds, 2023 Bond Funds, 2024 Bond Funds, Escrow Reimbursement Status:

E OWNSBY PKWY

Contruction contract has been awarded to McMahon. Construction is 40 percent completed.

PRESTON HILLS CIR

Project Status

D RR VE O L EC IRI A PR

Project Progress

CHURCHILL DR

HERITAGE TRL

COUNTY ROAD 83

QUAIL HOLLOW ST

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 12 of 69

Estimated Completion

Estimated Total Cost

January 2027

$14,320,000


SETTLERS RIDGE RD

COUNTY ROAD 95

STON RD

N LOUISIANA DR

COUNTY ROAD 101

Coit Rd Resurfacing

Project ID: R79

N PRE

Project Phase: Design Description: This project includes an asphalt resurfacing of Coit Rd in three segments. These segments are County Road 100 from Preston Rd to County Road 97, County Road 90 from County Road 92 to County Road 98, and County Road 97 from Lynn Stambaugh Pkwy to County Road 134.

W FM 455

N HAW

Road Capital Recovery Status: Construction ongoing and scheduled to be completed before the CISD 2026 Fall semester first day of school, August 12, 2026.

E SUNSET BLVD

OLD GLENDENNING RD

Project Status

Funding:

S COIT RD

S PR EST ON RD

S OKLAHOMA DR

COUNTY ROAD 98

COUNTY ROAD 127

S

N OK

EE

TRL

LAH O

MA DR

LYNN STAMBAUGH PKWY

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project Progress

Project 13 of 69

Estimated Completion

Estimated Total Cost

November 2026

$2,050,000


Coit Road Improvements (Choate Pkwy to Outer Loop) Project ID: R67 Project Phase: Design

E OUTER L OOP

S COIT RD

HACKBERRY CIR

Description:

SUMMERVIEW LN

This project consists of the reconstruction of the existing two-lane asphalt roadway road as a four-lane divided primary arterial within the ultimate right-ofway of a six-lane divided arterial. Drainage, signage, and pavement markings will be included in the project. Lighting and landscaping are not included in this project. Funding: 2023 Bond Funds, 2024 Bond Funds Status: The City is awaiting the closing of the title for one remaining property needed to acquire the necessary right-of-way. Utility coordination is underway, and the City is currently waiting on franchised utility plans for relocation.

CHOATE PKWY

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 14 of 69

Estimated Completion

Estimated Total Cost

February 2027

$4,445,000


W FM 428

CR 52 (Celina Pkwy) Reconstruction

FM 428

Project ID: R82 W GLENDENNING PKWY

as

Pk

COUNTY ROAD 51

wy

W FM 428

Full depth reclamation/replacement of the asphalt pavement from Collin County Outer Loop (CCOL) to FM 428 with HP pipe underground drainage system south to the CCOL. OLD LOG TRL

ST

DALDORAN DR

EMMANUEL LN

S CELINA PKWY

S Dal l

Description:

S DALLAS PKWY

Funding: 2023 Bond Funds, 2024 Bond Funds Status:

Y COVENTR

y

DR

la s P k w

W OUTER LOOP

HUDD

s Pk wy

LESTON

S Dal

S D a ll a

DR

Contract awarded at December 2025 Council. Construction started at the end of February. Substantial completion is anticipated by mid August 2026. $3.5M was available for the project, while cost came in at $7.0M. Scope had to be cut from the project. The project went from a 29' B-B curbed, concrete road to full depth reclamation and resurfacing of the existing asphalt road for a new cost of $2.4M. The project is now on track to be completed before the start of the 2026 school year.

COUNTY ROAD 52

KE O O BR IS R CA

Project Phase: Construction

COUNTY ROAD 53

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

NOTT INGH AM R D

Project Status

Project Progress

Project 15 of 69

Estimated Completion

Estimated Total Cost

August 2026

$2,615,400


CR 53 Rehab and Old Log Trl Extension RL OG T OLD L

W OUTE

R LOOP

Project ID: R42 Project Phase: Design Description:

W

The project entails widening and improving County Road 53 surface from gravel to concrete west of the BNSF railroad tracks to the edge of the floodplain along Doe Branch Creek.

OP LO R TE OU

Funding: 2021 Bond Funds, 2022 Bond Funds, Road Capital Recovery Status: 100% plans completed. This project has been removed from the Five-Year CIP.

COUNTY ROAD 53

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

Project Status

Project Progress

Project 16 of 69

Estimated Completion

Estimated Total Cost

TBD

$2,750,000


P r os pe ct S t

Fo xw oo d St

H al e Rd

Gree ne St

H a l e Rd

Hanc oc

st o le dd

Hu

Project ID: R55 Project Phase: Design

SWEETWATER WAY

Description: The initial phase of this project includes traffic signal studies, as well as design and installation of traffic signals along the North Dallas Pkwy at Light Farms Way, Punk Carter Pkwy, Collin County Outer Loop, and FM 428. This project also includes the construction U-turn lanes at each intersection and additional pavement width not within the scope of the North Texas Toll Authority (NTTA) DNT project.

N TY

id e D r

ROAD 50

Sunny s

Da lla s Pk wy Y

ford

Ln

W a ve rl y D r

ay B el lc re st W

F ul le r D r

Funding:

F

ar RM m Ss W W AY

2023 Bond Funds, Road Capital Recovery Roadway Impact (Zone 6) n

ay

oa d 50

S DALLAS PKW

yR

t A gh F L iH T

nt

Y

SSDALLAS PKW

Cou

g Lan

L IG

S D a ll a s P kw y

CO U

RD r E Dr e

D ev o

o

Pk w

st

as

all SD

W

ay

on st

ag

e

ill

M

d

n eL

g

ay W

r

on

D

yt

ssl

d an

Al

c

Ln

Contact: Linda Majeed 469-813-4189 o e LMajeed@celina-tx.gov

is

ac

r

Br

Lil

D

le

on No

Co t t o nw o

od

G ra

Project Progress

d

ti

s

ay

on

W

y Wa

Status:

Signal design plans are completed. The construction R d for the signals at Punk Carter Pkwy and Light contract ma n Cush Farms Way was awarded in March 2026. Awaiting delivery of the signal materials. Construction is anticipated to begin in Fall 2026. The Doe Branch CLOMR is under review by FEMA.

ay

R

rm

W

wy

lW

e

Pk

ek

L

ry

as

re

er

ild

Fa

all

sC

y fl

ow

y

e he

ROAD 970 COUNTY Co unty Road 970

Project Status

es

Wa

W

W

pr

ak

ht

Cy

O

Lig

r

D

Po

ve

y

Gr

Sk

DEVON S HI Rs h i n

SD

t Q ueensw ay C

Somerse t

Bur

Dallas North Tollway (DNT) Intersection Improvements

Culve r Ave Culver A v e

W P unk Carter Pkwy

W PUNK CARTER PKWY

g Rd

W Punk Carter P kw y

y

wy

Cou nty Road 50

ing Way

Chest er Dr

Ep p

Pkw y

Prince to n Dr

Dr

Project 17 of 69

Estimated Completion

Estimated Total Cost

July 2027

$4,530,000


O'BRIEN DR

Dallas Pkwy 42" and 36” Water Line - Celina Rd Pump Station to J. Fred Smith Pkwy COUNTY ROAD 57

Project ID: W50 Project Phase: Design

W FM 455

RAWHIDE RD

COUNTY ROAD 9

N DALLAS PKWY

W J FRED SMITH PKWY

Description: This project will fund right-of-way acquisition and construct a 54” water line on Dallas Pkwy from the Celina Rd Pump Station to J. Fred Smith Pkwy. This project will provide additional water supply to the northwest section of the City. Funding:

COUNTY ROAD 8

2021 Bond Funds, 2023 Bond Funds

SMILEY RD

COUNTY ROAD 54

Status: S DALLAS PKWY

Construction to start in 2027-2028.

FM 428

CELINA RD

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project Status

Project Progress

Project 18 of 69

Estimated Completion

Estimated Total Cost

TBD

$22,440,000


A DR PLE S T

N OK LAHO MA D R

W BEE

Project ID: B33

N OH IO ST

W MA

Downtown Center & Parking Garage

N LOU ISIAN

ZONA DR N A RI

ST

DR

N CO LORA DO

N FLORIDA DR

N ILLI

N O IS

BODARK LN

CH ST

W PEC AN ST

W WALNUT ST

Project Phase: Construction Description: Construction of ~400 space parking garage on the east side of Arizona between Walnut (FM 455) and Pecan. Construction of ~100,000 square feet library on the west side of Colorado between Walnut and Pecan. Funding: 2023 Bond Funds, 2024 Bond Funds

AHOM A DR

A DR S LOU ISIAN

DR

K ST

Project Progress

S OKL

ST

O ST

ST

W ELM

W ASH ST

Project Status

Garage TCO granted on October 18, 2025 for three floors with top floor remaining closed for construction material lay-down space for CMAR. Building construction underway and currently on schedule.

IN ST

S OHI

BAMA

W OA

W MA

S COL ORAD O

S AL A

S A RI Z ONA DR

Status:

E ELM

ST

Contact: Barbara Hoskins 940-453-7018 BHoskins@celina-tx.gov

Project 19 of 69

Estimated Completion

Estimated Total Cost

February 2027

$96,000,035


Downtown Inner Loop Phase 1 KOA ST

Project ID: R20

Description: Roadway, drainage, water, and sewer improvements on Colorado Dr, Beech St, Ohio St, and Pecan St.

N NE W

MEXIC O

DR

E MALONE ST

PLE S T

N OK LAHO MA D R

CH ST

Project Phase: Construction

N OH IO ST

W MA

W BEE

N LOU ISIAN

ST

ZONA DR N A RI

N CO LORA DO

DR NOIS N IL L I

N FLORIDA DR

A DR

BODARK LN

E BEEC H ST

W PEC AN ST W WALNUT ST

Funding: 2017 Bond Funds, 2018 Bond Funds, 2021 Bond Funds, 2022 Bond Funds. Status: ATT have been permitted to complete the removal of overhead fiber lines along Ohio St. Remaining overhead poles to be removed to complete brick paving.

E PEC AN ST

E WA W MA

W ELM

Project Status

LNUT

ST

IN ST

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

ST

Project Progress

Project 20 of 69

Estimated Completion

Estimated Total Cost

October 2026

$7,390,000


DR

LA KE VIE W

n Rd N P re st o n Rd

Project ID: S41 STANFORD LN

R dN P REST ON R D

rest NP

LYNN STAMBAUGH PKWY Ly nn St ambaugh Pkwy

AHOMA

DR

N CELINA PKWY

W W

Rd

on NP 289

100% plans completed. Construction to start in 2028.

289

W FM 455

E ASH

ST

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

W SUNSET BLVD

Project Status

SP

res

289C

Status:

t o n S PR R d EST ON RD

O ST S COL ORAD

S ARIZ ONA DR

TOLLESON DR

S ALABAMA DR

STEFHANIE DR

W F M 455

T P e E PECSAt N S can

ST

W OAK ST W ASH ST

E

S OKL AHOM A DR

W FM 428

St

2023 Bond Funds W FM 455

F M 455

W ELM

Funding:

W

W MA IN ST

a l nut

Description:

rest

N OKL

W PEC AN ST

WW W Walnut St ALNUT ST

E MALONE ST

Project Phase: Design

This project will upsize a series of undersized gravity sewer lines in the Downtown area beginning at Preston Rd and extending west toward the Downtown wastewater treatment plant (WWTP). The project includes two phases: Phase 1 from WWTP on Florida Ly n n Sta m baugh Pkwy to Oklahoma and Phase 2 from Oklahoma to east of Preston Rd (SH 289).

on

N FLORIDA DR

N LOUISIANA DR N Lo uisiana Dr

COUNTY ROAD 57

FM 428

SETTLERS RIDGE RD

N P re s to

COUNTY ROAD 95

Downtown Sewer Improvements

Project Progress

Project 21 of 69

Estimated Completion

Estimated Total Cost

TBD

$10,300,000


Downtown Water Reclamation Facility Phase II COUNTY ROAD 57

Project ID: S25 Project Phase: Design G BAR TRL

Description:

N FLORIDA DR

The existing Wastewater Treatment Plant (WWTP) can serve a treatment capacity of 0.95 million gallons per day (MGD). This project will expand the existing treatment capacity from 0.95 MGD to 2.0 MGD. The impact fee study identifed an expansion of the Downtown treatment plant to 5.0 MGD by 2030. This project has been identifed as 1A. The remaining four expansions will be in 1.0 MGD increments and will be label 1B (3.0 MGD), 1C (4.0 MGD) and 1D (5.0 MGD). Funding:

OUTPOST TRL

Wastewater Impact Fees Status: Construction contract awarded during July Council meeting. Contract to be finalized and pre-construction meeting to be scheduled next.

KOA ST

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

BODARK LN

Project Status

Project Progress

Project 22 of 69

Estimated Completion

Estimated Total Cost

January 2029

$130,863,000


W FM 455

LNUT

E PECAN ST

ST

Project ID: R46 Project Phase: Design Description:

N ST

Design and reconstruction of E. Elm Street (from Preston Road to S. Texas), E. Oak Street (from E. Elm Street to E. Ash Street) and S. Texas Drive (from S.Texas to S. Arkansas Street)

S NE W

E MAI

MEXIC O

DR

E WA

S ST

ST

S A RK ANSA

E ELM

Funding: Roadway Capital Funds

ST

Status: EST ON R

D

E OAK

E. Elm Street, E. Oak Street and S. Texas Drive

S PR

A DR HOM KLA SO

Schematic design is completed. The design contract was awarded to Garver by Council in July 2026. 30% Plans to be submitted to the city in August 2026.

E ASH

ST

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 23 of 69

Estimated Completion

Estimated Total Cost

May 2027

$7,070,000


CO

Emergency Signals Phase II RY DR NT VE

Project ID: F25 LEST ON DR

Description:

DD

C TA VIS

DR BB A CN M

Project Phase: Design

W OUTER LOOP

HU

NOT TING H

OW AD ME

AM RD

FM 428 W

Design and construction of four emergency sirens to be placed throughout the City.

S LEGACY DR

SMILEY RD

LIGHT FARMS WAY

S PKWY S DALLA

COUNTY ROAD 50

IR

W

NK PU

Y KW P ER RT CA

Funding: Integrity Fund Status:

DE

R

S U N RIS E L N

P R AIRIE C R O S SIN G

M

N EA

AY W

DOE BRANCH BLVD

CAREY RD

Originally the project was for two signals. Two additional signals for a total of four were requested. Requested design change order from engineer. Disruption was due to additional sirens being requested. Project is with purchasing for bidding.

W FRONTIER PKWY

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

Project 24 of 69

Estimated Completion

Estimated Total Cost

December 2026

TBD


SLATE LN

Fire Station #4

EVERGREEN TRL

BERRY ST

KINSHIP PKWY

BLUEBIRD W AY

INDI

GO

Project ID: F23 Project Phase: Design Description:

LN

Design and construction of three double bay Fire Station with storm shelter and fire training tower. PUNK CARTER PKWY

Funding: OAKDALE DR

LAWNDALE ST

S COIT RD

AZURE LN

BLU EW OO DW AY

RO YAL LN

R57-8502-624, FY 24 Bonds, 2023, 2024, 2025 Bonds Status: Underground utilities are in and parking / building concrete poured, awaiting vertical construction release.

COBALT DR

Contact: Barbara Hoskins 940-453-7018 BHoskins@celina-tx.gov

Project Status

Project Progress

Project 25 of 69

Estimated Completion

Estimated Total Cost

February 2027

$12,231,313


28

T he R a n c h

FM 428 (Glendenning Pkwy) Water Line Relocations

Rd

Project ID: W71

RA N

Project Phase: Design

FM 428

This project is for the relocation of two existing water lines on Glendenning Pkwy (FM 428) between DNT and Preston Rd. This relocation is necessitated by the realignment of Glendenning Pkwy (FM 428) from Dallas Pkwy to Preston Rd. Funding:

S Celina Pkwy

W FM 4 28

Description:

County R oad 5 5

d

W FM 428

R RDa nc h CHe R

Th

W GLENDENNING PKWY

W Glende nning Pk wy

Escrow Reimbursement

Plans are ready. Awaiting easement aquisition and reimbursement agreement with TxDOT.

Ave

r ossi ng Dr

W esterk irk Dr

A

N

R

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 26 of 69

t a rt C

Project Progress i sh

Project Status

St A nd rew

s

D

r

D

Alan Dr

Renw ick Dr

DA L

D OR

OLD LOG TRL

Bretallow Dr

Rhea Ct

Dean Ct

Glen C

Li thg ow Rd

Greenway Ave

Es k

County Road 1117

Buckley St

EM E mm an ue l Ln MANUEL LN

Ross Av e

Pec os Dr

S CELINA PKWY

W Glenden ning Pkwy

Status: Fu lfo rd Ct

S Celina Pkwy

TH E

W

Estimated Completion

Estimated Total Cost

TBD

$10,650,000


Frontier Middle School - School Zone Traffic Control

FM 2478

Project ID: R102 Project Phase: Design

MILL POND DR

Description: Signing and striping plans for a school zone for the new PISD middle school #8 located at the northeast corner of Frontier Pkwy and Mill Pond Dr. Funding:

E FRONTIER PKWY

Road Capital Recovery Fund Status: Plans have been completed and Public Works Department is working on signs installation. Work is to be completed before school resumes in August 2026.

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 27 of 69

Estimated Completion

Estimated Total Cost

August 2026

$230,000


COUNTY ROAD 50

PK WY

Design of four lanes of concrete from FM 1385 to Dallas Pkwy. W FRONTIER PKWY

Funding:

BO TH

WE

Project Phase: Design Description:

M

LL BLVD

EA N D

ER

FM 1385

W AY

SMILEY RD

CAREY RD

Frontier Pkwy (Parvin Rd) - FM 1385 to Dallas Pkwy Project ID: R22

SD AL LA S

NK PU

BRANCH BLVD DOE

W

S LEGACY DR

W

Y W PK R E RT CA

MCNABB DR

FM

8 42

LIGHT FARMS WAY

W OUTER LOOP

2019 Bond Funds, 2021 Bond Funds, Road Capital, Recovery, Escrow Reimbursement

PARVIN RD

Status: Sixty percent (60%) design plans have been submitted and reviewed. Ninety percent (90%) design plans underway. Right‑of‑way acquisition and utility relocation ongoing.

A

rooke Ave wB rro W FIRST ST

MA GN OL IA

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

BL VD

Project Status

Unive rs ity D r

Project Progress

US Highway 380 W

Project 28 of 69

Estimated Completion

Estimated Total Cost

TBD

$84,748,000


Falc on C t

Ag

a ve

Dr

n

Dr

ucc a Ln

ne r

ea f Ln

Cor

Frontier Pkwy Water Line

Blue bon net Ln T win La k es Dr

ER DR CORN Daisy Corner Dr

co Fa l

Ln

Snow drop Dr

a na L n

Carn ation St

Che rry Blo ss o m Ln

Lily

Twi n Lak es Dr

FALCON RD Fal con Rd

S COI

T RD

m i ne L n

M a ri g o l d

S Coit Rd

LLS CIR PRESTON HI Pre sto n Hi ll s C ir

TWIN LAKES DR

Bird C herry Ln

Ja s

n

Rd

D AISY

Red Ro se Trl

Project ID: W16 Project Phase: Design Description:

This project will replace the existing 6” water line with a 12” water line along Frontier Pkwy from east of Preston Rd to Coit Rd. This project is being completed due to Gard enia St the widening of Frontier Pkwy (FM 1461) from Preston Rd to Custer Rd by TxDOT.

Snapdragon Ct

ow s D r

2021 Bond Funds, 2022 Bond Funds, Water Capital Recovery Status: tD Fo

H

res

ig

hl

Remi ngton Rd Reming to n Rd

r

an

dM

ead

Dr bstone Dr Tombstone Tom

ue

Fa i r O

Fair Oak s Ln

aks L n

D

ow

ad a dow

D

Dr N Coit Rd

Project Progress

Me

Cr

k oo

ed

St

ick

Ridge

W ood

Whi sp erin g Mea dow s Way

Project Status

Dr

n Dr h ave

R ock

e Dr n Ridge Du bl in Ri dgDubli

Blue Fores t D r

Wichita Dr

st y

r

Win dy Hill Ln

Cattle Dr

Lones ome D ove Dr

Mi

MD irs t y

Me

Win ches ter D r

Wichit a Dr

The Frontier Pkwy widening is currently delayed without an anticipated construction start date. The water line relocation will be completed when developments come along Frontier. Section of the water line from Preston Hills Cir to the western boundary of Twin Lakes Dr subdivision will be installed with the Millen Farms development through a reimbursement agreement.

r

F ai r O a ks Ln

Bl

Chisholm Trl

C attle Dr

Chisho l m Trl

Funding:

E Frontier Pkw y

N Coit R d

C heyenne Dr

S anta Fe LnSanta Fe Ln

Bozma n Trl

E FRONTIER PKWY

E Fro ntier Pk wy

E Fro ntier Pk wy

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 29 of 69

Estimated Completion

Estimated Total Cost

TBD

$1,700,000


W FM 42

COUNTY ROAD 8

N

Glendenning Pkwy - Celina Rd Pump Station to Celina Pkwy 54" Water Line

D

al

la

s

Pk

w

y

Project ID: W83 RD

D

THE RANCH

COUNTY ROAD 54

N D al las Pkwy S DALLAS PKWY

a

Project Phase: Design

W SUNS ET BL VD

Description:

l la

s Pk

wy W F M 4 28

FM 428

Funding:

kw

y

8

S Da lla

sP

W FM

42

W FM 428

2025 Bond Funds Status: 90% plans were submitted for review on July 1, 2026.

COUNTY ROAD 52

HUDDLESTON DR

S CELINA PKWY

LN

s Pk wy

KEN SIN GT ON

S D a ll a

Y DR NTR VE CO

FM 428 W W F M 428

Project Status

The project includes the proposed 54" Transmission Pipeline. The 54" Pipeline will connect to the 54" stub near the intersection of FM 428 and CR 55. The Pipeline generally follows the proposed FM 428 rightof-way west until reaching the Celina Rd Pump Station site. The approximate length of pipe is 11,000-linear feet.

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

P W OUTER LOO

Project Progress

Project 30 of 69

Estimated Completion

Estimated Total Cost

March 2028

$16,750,000


W OA K ST

W

COUNTY ROAD 8

289

Glendenning Pkwy (Dallas Pkwy to Preston Rd)

W ASH ST

S OKLAHOMA DR

Pk wy

W F M 4 28

sP k S DALLASwPKWY y

Rd

on

Description:

rest

s FM 428

This project will include the reconstruction of the existing two-lane asphalt road into a four-lane divided primary arterial within the ultimate row of a six-lane divided arterial. This project will include right-of-way acquisition, drainage, bridge, and sign and pavement markings. Lighting and landscaping will occur as part of a separate project. This project will be a shared project between the City and Texas Department of Transportation (TxDOT).

289

Funding:

W GLENDENNING PKWY

OLD LOG TRL

Escrow Reimbursement

289

E

E OUT

OO RL

P

s Pk wy

Project Progress

Schematic design and environmental analysis completed. Design is funded with the 30% plans anticipated to be completed by Feburary 2027; 60% by August 2027; 95% by April 2028; 100% by September 2028. Construction funds are not available at the moment.

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

OP W OUTER LO

COUNTY ROAD 53

Project Status

Status:

S Pres t o n R d

S D a ll a

COUNTY ROAD 52

S CELINA PKWY

S Da lla HUDDLESTON DR

Project Phase: Design

SP

l la

W FM 428

Project ID: R15

S SPPr R eE s tSoTn ON R dRD

a

W SUNS ET BL VD

S Bus ines s 2 89

D

THE RANCH

RD

SP

res

t on

Rd

289C

289

Project 31 of 69

Estimated Completion

Estimated Total Cost

TBD

TBD


HIllside Dr Concrete Replacement KOA ST

BODARK LN

Project ID: R101 Project Phase: Construction

N CELINA PKWY

N FLORIDA DR

Description: Remove and Replace existing Hillside Dr pavement. Funding: 2022 Bond Funds, 2024 Bond Funds, 2025 Bond Funds W PECA N ST

Status: Construction contract awarded March 2026. Construction is 40% completed.

W FM 455

W WALNUT ST

Contact: Scott Harper 469-731-3996 SHarper@celina-tx.gov

Project Status

Project Progress

Project 32 of 69

Estimated Completion

Estimated Total Cost

January 2027

$960,250


A DR N LOU ISIAN

ST N CO LORA DO

PLE S T

Description:

E BEEC H ST

MEXIC O N NE W

E WA

Project Status

AHOM A DR S OKL

A DR

S OHI

S LOU ISIAN

K ST

S COL ORAD O

W OA

ST

ST

O ST

IN ST

Project Progress

E MAI

E ELM

The project consist of pavement, signing, and striping improvements at the intersection to facilitate safe pedestrian crossing and comply with PROWAG requirements. Funding:

DR

W PEC AN ST

W MA

W ELM

N TEXAS DR

N OH IO ST

CH ST

Project ID: R122 Project Phase: Design

N A RI

UT ST

S A RI Z ONA DR

W WALN

ZONA DR

W BEE

E MALONE S T

N OK LAHO MA D R

DR NOIS N IL L I

W MA

Intersection Improvements at Louisiana Dr and Pecan St

2025 Bond Funds E PEC AN ST

Status: The 60% Plans have been submitted for City's review.

LNUT

ST

N ST

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

ST

Project 33 of 69

Estimated Completion

Estimated Total Cost

TBD

$255,125


N

97

Rol

KL OOL n BR o k

Bro

J Fred Smith Water Line (Preston Rd to Coit Rd)

lin

N

LLI ROl s

gH

Br

L HIL

N COIT RD

NG

Project ID: W67 oo k Ln

LAK EVI E DR W D

r James Rd

97

a

n sL

Tidwell Ln

und

K i nney Dr

C lay ton Ln

Bo

Kinn ey Dr

BATEMAN LN B t e m an Ln

Ln

Rd

Misso uri St

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Lynn Sta mb augh Pkwy

Geer Rd

Sha de Tree L n

LYNN STAMBAUGH PKWY

Lynn Stambaugh Pk wy

ton

100% plans completed. Construction funding currently scheduled for FY 2028.

Stone Ln

D rake Ln

res

Status:

Bre w e r Ln

Re dbu d St

NP

2023 Bond Funds

C ounty Road 9 7

st on R d

N PR ESTO NNP rReD

Caru t h Ln CARU TH LN

STANFORD LN Stanford

n

Lin dy L n

L i nd y L

ty Ro

tlers

Settler s Rdg

Funding:

ad

RIDGE RD SETTLERS Set Ri dge Rd

N COIT RD C o un

ew

W illard Ln

n Rd

i L a k ev

Fou nde rs Ln

Project Status

Description: This project includes the construction of a 24” water line on J. Fred Smith Pkwy from Preston Rd to Coit Rd to provide additional redundancy to serve the highpressure plane located east of Preston Rd.

N P r e s to

County Road

ls

N P r e st o n

g H

Rd

Rolli n

95 COUNTY ROAD 95

Project Phase: Design

Project Progress

Project 34 of 69

Estimated Completion

Estimated Total Cost

TBD

$3,170,000


W F M 428

MEADOW VISTA CIR

MAN CHE STE R Y WA DS N LA AT FL

TON DR DING PAD

HUDDLESTON DR

LN

CT

D AM R INGH T T NO

CN

AB B DR

COUNTY ROAD 50

M

S LEGACY DR

Description:

COUNTY ROAD 7

Y AS PKW S DALL

Y KW R RP D E T R EN CA RD GA PUNK W

Project Phase: Design

s Pk wy

KEN SIN GT ON

Project ID: R96 S D a ll a

FM 428 W

Y DR NTR VE CO

PRIVATE ROAD 902

Legacy Dr - Carey Rd to Punk Carter Pkwy

Design of the 1st 4 lanes of the six lane divided thoroughfare including major storm improvements including bridge class culverts to convey the 100 year floodplain and creek, FEMA and WOUS coordination, Roundabout at Legacy Dr and Punk Carter Pkwy, Roundabout at Carey Rd and Legacy Dr, improvements to FM 428 and Legacy Dr intersection, and improvements to existing water and wastewater infrastructure as needed to avoid conflicts with proposed design. Funding:

S D a lla s Pk

wy

Roadway Impact (Zone 6)

Project 35 of 69

Pk

wy

COUNTY ROAD 970

Estimated Completion as

Project Progress

Contact: Scott Harper 469-731-3996 SHarper@celina-tx.gov

all

Project Status

Design contract was awarded to Westwood by Council in May 2026. 60% Plans are to submitted in January 2027.

Estimated Total Cost

SD

DOE BRANCH BLVD

CAREY RD

Status:

December 2030

TBD


lD

S Legacy D

od D r

r

Ow

Legacy Dr - Honey Creek to Carey Rd

r

Pl agge Rd

Project ID: R28

cy

S L e ga

Ca rey Rd

Description: Construction of three-lane concrete roadway, including a bridge. Funding:

DOE BRANCH

S LEGACY DR

BL VD

CAREY RD

Carey Rd

Priv ate Road 5 156

Dr

Project Phase: Construction

ad 5

Status:

4 05

Construction funding currently scheduled for FY 2029.

te

Ro

2021 Bond Funds, Road Capital Recovery

e ar

Cr

Hac kberry Creek Trl

Cl e

Hi g Highland Ba yo u D r

Keechi Creek Dr

i a n Ri v er D r

Platte Rive r T rl

y

na d

Project Progress

Wa

Ca

Project Status

Cibo lo Cree k Trl

D

ra nch Bl v d

r

ek

an

a

r

hl

ive

w

Estimated Completion

Contact: Scott Harper 469-731-3996 SHarper@celina-tx.gov

TBD

Project 36 of 69

Estimated Total Cost

eB

rT ve Ri

tte

nR

in

lvd

d ia

re

d

Ba

C a na

Driftw ood Creek Trl

hB

Ra

yo

TrS P l R ING CREEK TRL

Clear Creek Pkwy

l u Dr

ek

CLEAR CREEK PKWY

k wy kP

rC

Pla

e

re

Do

r

Dr

te

R TD PO

YA DR

ER

o am

iv er

S pr i n g C

nc

FL OW KE

Al

SC RI

N

ST

R sa

re e k Trl on C

Do e B r a

EA M

R DE

AY W

PT

c Ch a

iv er D r S L ega c y D r

nR

Wood Rive r Trl

Cim

o a rr

P ri v a

$57,320,000


Legacy Dr Extention to Louisianna Dr

Y KW RP E Z L STE

Project ID: R111

PRES TON LAK ES D R

G

COUNTY ROAD 59

BO

AY TW R A

Project Phase: Design Description:

COUNTY ROAD 58

N CELINA PKWY

Extension of 3700’ of Legacy Dr to connect Carthage Dr and Louisiana Dr. This project is associated with the Developer Agreement for Acadia in Legacy Hills. Funding:

N LEGACY DR 289C

E CARTHAGE RD

Carthage Rd

2023 Bonds Funds Status:

ABBOTT CREEK RD W GA MOORE PKWY

GOLDEN RAINTREE RD

VIBURNUM WAY

N LOUISIANA DR N L ouisiana Dr

D RD NAR

BAR

PAYRONE RD

RODEO RANCH ST

BARN SWALLOW DR

Staff has received and reviewed 60% plans. Waiting for 90% resubmittal.

GALILEO ST

E GA MOORE PKWY

Project Status

Project Progress

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project 37 of 69

Estimated Completion

Estimated Total Cost

December 2027

$2,720,000


D

a

l la s

Legacy Dr Water Line (Punk Carter Pkwy to Celina Rd Pump Station)

Pk

wy

Project ID: W62

FM 428

W FM 428

kw

sP

S Da lla

Description:

W F M 428

Y PKW DR RTER N E CA RD GA PUNK W

TON DR DING PAD

LN

CT

S DALLAS PKWY

HUDDLESTON DR

Status: Design plans are 90% completed, and awaiting Legacy Dr schematic project (R96) results to resume design.

W OUTER LOOP

D AM R INGH T T NO COUNTY ROAD 50

DR Y WA BB A DS N N C LA M AT FL

S LEGACY DR

MAN CHE STE R

2023 Bond Funds

s Pk wy

KEN SIN GT ON

Funding:

S D a ll a

Y DR NTR VE CO

PRIVATE ROAD 902

This project includes the design and construction of a 24” and 36” water line along Legacy Dr from Punk Carter Pkwy to Celina Rd Pump Station.

FM 428 W

MEADOW VISTA CIR

Project Phase: Design

y

8

W FM

42

CELINA RD

COUNTY ROAD 7

Project Progress

S D a llas Pk w y

Project Status

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project 38 of 69

Estimated Completion

Estimated Total Cost

TBD

$5,700,000


Legacy Hills Wastewater Reclamation Facility Phase II Project ID: S59 Project Phase: Design Description: W FM 455

N DALLAS PKWY

This project is the design and construction of an additional treatment capacity at the existing Legacy Hills WRF. The existing plant was constructed in 2024 and designed to serve 0.95 million gallons per day. Due to the continued growth of the Legacy Hills subdivision and the continued expansion of the Little Elm Creek and Honey Creek sewer basins, additional capacity is needed at the Legacy Hills WRF. This project will expand the treatment capacity from 0.95 MGD to 2.0 MGD. Funding: 2024 Bond Funds Status: 100% design plans reviewed. Construction funding currently scheduled for FY 2029.

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 39 of 69

Estimated Completion

Estimated Total Cost

TBD

$31,762,000


Low Pressure Plane #2 Elevated Storage Tank

COUNTY ROAD 57

W J FRED SMITH PKWY

Project ID: W81 Project Phase: Design Description: This project includes the design and construction of a proposed 3.0 million gallon (MG) composite elevated storage tank (EST) for potable water that will be located on a 1.98 acre tract at the northwest corner of the proposed Ranch at Uptown Phase 1 subdivision.

COTTONTAIL WAY

BUCK TRL

Project Status

TO UP

Project Progress

N W

HR NC A R

Status: RANGELAND RD

TROTTER LN

L

HAYLOFT LN

R SP CK O

S TR I NG

2025 Bond Funds, 2027 Bond Funds, 2028 Bond Funds, 2029 Bond Funds

DAMESFLY DR

R

W FM 455

Funding:

Design plans are 90% completed. Awaiting construction funding availability for 100% plans completion.

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

D

Project 40 of 69

Estimated Completion

Estimated Total Cost

December 2027

$19,729,000


Marilee Rd (Preston Rd to N. Dallas Pkwy) Project ID: R84 Project Phase: Design Description: This project consists of the full-depth reclamation of the existing asphalt roadway on Marilee Rd from Preston Rd to Dallas Pkwy. This project will be shared with the City of Gunter, Grayson County, Collin County, City of Celina, and the adjacent subdivision developers.

COUNTY ROAD 60

Funding: COUNTY ROAD 58

Road Capital Recovery

Project Status

Project Progress

Design is completed and waiting on funding to determine timeline for bidding.

N PRESTON RD

COUNTY ROAD 59

COUNTY ROAD 106

PRESTON LAK ES DR

N CELINA PKWY

N DALLAS PKWY

COUNTY ROAD 10

Status:

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 41 of 69

Estimated Completion

Estimated Total Cost

April 2027

$8,700,000


N LEGACY DR

N CELINA PKWY

Mustang Meter Conversion COUNTY ROAD 58

Project ID: W78 Project Phase: Design

COUNTY ROAD 134

Description:

COUNTY ROAD 101

CO UN TY RO AD

Funding: Utility Impact Fee Fund Status: Awaiting 100% submittal. Need coordination with Mustang for the tentative date of service transfer.

57

COUNTY ROAD 9

W J FRED SMITH PKWY

Converting Mustang water system/meters to the City of Celina water system. Meters are located west of Preston Rd.

N COIT RD

W FM 455

N PRESTO N RD

N LOUISIANA DR

N DALLAS PKWY

E GA MOORE PKWY

COUNTY ROAD 8

S DALLAS PKWY E SUNSET BLVD

Project Status

Project Progress

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project 42 of 69

Estimated Completion

Estimated Total Cost

December 2027

TBD


STANFORD LN Stanford

und

sL

n

Ln

Bo

st on R d

ESTO NNP rReD N PR

Project Status

Misso uri St

Geer Rd

ton res

2023 Bond Funds Status:

Creek C

od

sid

La ke

4

e Trl

r

SHAWNEE TRL

w ne

eD

wo

Sh a

oss Cr

Rd

AN ST St E PEEC Peca n

on

St a nsa s s a s SS tA rk

St

55

Project Progress

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

W FM 455

StElm St E Elm E

rk a n k St

S A

a Dr S Ok la h om

a Dr isia n

S L ou

S Ohi

E Oa

n

S Te xas St

o St

k St

W FM 455

rest

a Dr

lah om

St

Funding:

Lynn Sta mb augh Pkwy

W FM

W Elm

S Ok

St

W FM 455

ca

Installation of a 12” water line along the east side of Preston Rd from FM 455 to First Celina Baptist Church.

100% plans completed. Awaiting funding.

SP

E Pe

i s i a na

Main

D rake Ln

Rd ch St

t

Dr

l nut S

S Lou

W Wa

le St

N Oh

io St

E Bee

Description:

Fou nde rs Ln

N Tex as St

E Map

289C

E

Project Phase: Design

Stone Ln

LYNN STAMBAUGH PKWY

E Ma lone St

Project ID: W61

NP

N OKLAH

Dr

i si a na

N Lou

t

K i nney Dr

Tidwell Ln

t

ech S

t

Kinn ey Dr

B a t e m an Ln

Lynn Stambaugh Pk wy

E MALONE ST Malo ne St

N. Preston Rd 10” Water Upsize

Caru t h Ln

James Rd

Sha de Tree L n

W Be

ple S

L i nd y L

n

N LOUISIANA DR

Lin dy L n

W Ma

R AD M O

RDtlers Ri dge Rd SETTLERS RIDGE Set

Settler s Rdg

n Rd

95 COUNTY ROAD County Road 95

N P r e s to

N L ou i s ian a D r

Co un ty Road 95

Project 43 of 69

Estimated Completion

Estimated Total Cost

TBD

$1,580,000


289

Fo ur W i

s Dr nd

Project ID: S26 Project Phase: Design

COUNTY ROAD 134

Description:

h w a y 2S8ta N PRESTON 9te H ig h D w a y 2 8R 9

Coun ty R oad 134

Upsize of existing 8” sewer line along Preston Rd with an approximately 2000’ of 18” sewer line and 690’ of 12” line from CR 99 (G.A. Moore Pkwy) to CR 134. R o de o D

Wa y

N COIT RD

G

S ta te H ig

A YW VALLEG r e enYV EN alle E R y

e Rd

Funding: Bandan a Dr

ous

Cou nty R oad 97

R a nch H

r

Lo g Cab in Dr

Wastewater Impact Fees Status: 100% plans completed. Awaiting funding.

Tap ad ero Ln 289

PKWY E GA MOORE E GA M oore Pkwy

Coun ty Roa d 100

Project Status

Project Progress

GA

MO O

RE P KWY

County R oad 97

n Rd

E

N P re st o

Moo re Pkwy

N. Preston Rd Sewer Upsize (CR 99 to CR 134)

County Ro ad 10 5

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

Project 44 of 69

Estimated Completion

Estimated Total Cost

TBD

$1,610,000


Ohio St and Louisiana Dr Reconstruction

IN ST

N ST

S OHI

Project Phase: Design Description: Design and reconstruction of Ohio St and Louisiana Dr from Ash St to the south end.

A DR S LOU ISIAN

ST

Funding: S COL ORAD O

S ARI

ST

E ASH

2023 Bonds Funds

ST

Status:

MA DR HO KLA

S UTAH DR

E OAK

SO

ZONA DR

W AS H ST

ST

S A RK ANSA

E ELM

Project ID: R100 S ST

K ST

O ST

W OA

E MAI

ST

S NE W

W ELM

MEXIC O

DR

W MA

90% Design complete. Design public meeting held on May 2026. Acquisition resolution for necessary easements scheduled for August Council.

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

Project 45 of 69

Estimated Completion

Estimated Total Cost

December 2027

$5,712,000


N CO LORA DO

ST

N LOU ISIAN

A DR

Oklahoma Dr – Pecan St to Malone Rd

Description: This project will include the design and construction of Oklahoma Dr from Pecan St to Malone Dr. The project will replace the existing asphalt roadway construction with two concrete lanes and associated drainage, signage, and pavement marking improvements. Lighting and landscaping along Oklahoma Dr will be included in this project.

E BEEC H ST

Funding: 2023 Bond Funds, Roadway Impact (Zone 6)

W WA

LNUT

ST

E WA W MA

E PECA

LNUT

N ST

Construction started May 2026. Change order No. 5 for BNSF asphalt to concrete crossing at Beech St to be presented in August Council.

ST

IN ST

E MAI W ELM

Status:

N NE W

N A RI

MEXIC O

DR

W PEC AN ST

N TEXAS DR

N OH IO ST

N OK LAHO MA D R

PLE S T

CH ST

ZONA DR

Project Phase: Construction E MALONE ST

W MA

W BEE

Project ID: R63

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

N ST

ST

Project Status

Project Progress

Project 46 of 69

Estimated Completion

Estimated Total Cost

October 2026

$3,036,000


Old Celina Park Restroom W FM 455

Project ID: P32 Project Phase: Construction Description: Design and construction of modular restrooms and additional paved trails at the Old Celina Park. Funding: Park Fees FM 428

Status: W ASH ST

PKW Y ZION

YELLOWSTONE DR

Preconstruction meeting for the civil work was held on October 15, 2025. Building will be prefabricated by Public Restroom Company and will be delivered on site in August 2026.

HOT SPR

Project Status

Project Progress

ING S WAY

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 47 of 69

Estimated Completion

Estimated Total Cost

October 2026

$1,240,000


Ousley Park Stream Restoration E WA

LNUT

E PECAN ST

ST

DR

Project ID: P25 MEXIC O

N ST

Description:

S NE W

E MAI

Project Phase: Construction

S ST

ST

Status:

ST

Preconstruction meeting was held on April 14, 2026 and construction started June 22, 2026.

D

E OAK

2023 Bond Funds

EST ON R

AHOM A DR

S A RK ANSA

Funding:

E ASH

S PR

S OKL

S LOU ISIAN

A DR

E ELM

Stream Restoration and Trail Design along Doe Branch Creek from Preston Rd to Ash St.

ST

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 48 of 69

Estimated Completion

Estimated Total Cost

November 2027

$18,250,000


Parallel Doe Branch Interceptor – Parvin Rd to Legacy Dr Project ID: S58 S LEGACY DR

Project Phase: Design Description:

PRIVATE ROAD 5405

A CIM

DR RIVER N RRO

CR CON A H C

EEK TR

L

The parallel Doe Branch interceptor is a series of sewer lines that will begin at Parvin Rd and extend to the Frontier Pkwy lift station on the east side of town. The project is broken down into four phases Parvin Rd to Legacy Dr (15A), Legacy Dr to Preston Rd (15B), Preston Rd to Coit Rd (15C), and Coit Rd to Frontier lift station (15D). The total project will include the installation of 31,320 linear feet (LF) of wastewater lines between 36” and 48”. This project consists of the design and installation of approximately 1,500 LF 36”, 3,600 LF of 42” and 13,800 LF 48” gravity sewer associated interconnects. The FY 2025 project includes the design of the phase of the project from Parvin Rd to Legacy Dr in coordination with the development of the adjacent subdivision. Funding:

I

Status: CLEAR CREEK PKWY

A

AL

R SA O AM

DR VE R

WOOD RIVER TRL

IVY LEAVES DR

2021 Bond Funds, 2023 Bond Funds

TIN US

Waiting on 100% submittal. Construction funding currently scheduled for FY 2027.

BAYOU TRL

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

Project 49 of 69

Estimated Completion

Estimated Total Cost

TBD

$8,297,055


Parks Administration Building

MEXIC O

DR

E BEEC H ST

N NE W

Project ID: B36

DR

D EST ON R

ST

Funding: 2022 Bond Funds, 2023 Bond Funds, 2025 Bond Funds

S ST

ST

Status:

S A RK ANSA

E ELM

Design and construction of 14,000-square-foot Parks Administration facility of which 9,000-square-foot are for public use and programming space. This building is a rehab of the old Celina ISD athletic offices.

S PR

N ST

S NE W

E MAI

LNUT

Description:

E PECAN ST

MEXIC O

E WA

Project Phase: Construction

E OAK

A DR HOM KLA SO

E ASH

Project Status

Construction is underway of interior remodel. Exterior firelane, landscaping and utilities are forthcoming with timing completed simultaneously with building opening.

ST

ST

Contact: Barbara Hoskins 940-453-7018 BHoskins@celina-tx.gov

Project Progress

Project 50 of 69

Estimated Completion

Estimated Total Cost

November 2026

$10,000,000


Parvin Wastewater Reclamation Facility (WRF) & Hydraulics and Hydrology Project ID: S44 Project Phase: Design Description: This project will fund the required hydraulics and hydrology study associated with the construction of a possible water reclamation facility located near the intersection of Parvin Rd and Smiley Rd. IL SM

Funding:

EY RD

Sewer Capital Recovery Fund Status: Permit has been submitted to TCEQ for review.

PARVIN RD

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 51 of 69

Estimated Completion

Estimated Total Cost

TBD

$120,000


KOA ST

Pecan St (Arizona Dr to Florida Dr), Illinois St (Walnut St to Beech St), and Arizona Dr (Pecan St to Beech ST

BODARK LN

N CO LORA DO

Description:

N OH IO ST

A DR

PLE S T

ZONA DR

W PEC AN ST

2024 Bond Funds, Road Capital Recovery Status: 90% design plans completed for original design. Easement acquisition underway. 60% plans for design amendment currently under review. This amendment includes concrete pavement improvements to Illinois St from FM 455 to Pecan St and additional drainage improvements along the existing channel from Illinois St to north of Beech St.

IN ST

ST

S COL OR A D O ST

W MA

W ELM

Contact: Dailyn Cruz 469-447-8952 DCruz@celina-tx.gov

W OAK ST

Project Status

Project Progress

This project will fund the design and reconstruction of Pecan St from Arizona Dr to Florida Dr with subsurface utilities and concrete pavement. Drainage, sign, and pavement marking improvements will also be included in the project. This design also includes the full depth reclamation/replacement of the asphalt pavement of Arizona Dr from Pecan St to Beech St, and Illinois St from Walnut St to Beech St. Funding:

N A RI

S A RI Z ONA DR

S ALABAMA DR

TOLLESON DR

CH ST

Project Phase: Design

N LOU ISIAN

DR NOIS N ILL I

N FLORIDA DR

W MA

W BEE

W WALNUT ST

Project ID: R86

Project 52 of 69

Estimated Completion

Estimated Total Cost

TBD

$6,697,700


Preston Hills Cir Drainage Improvements Project ID: D45

N HILLS CIR PRESTO

Project Phase: Design

S PRESTON RD

Description: Improve drainage on Preston Hills Cir. Funding: Drainage Funds Status: Pending H and H Model. Adding in an additional nearby drainage concern.

E FRONTIER PKWY

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

Project 53 of 69

Estimated Completion

Estimated Total Cost

April 2027

$376,000


S St a t e

Dr

Preston Lakes Drainage Improvements

C ES AK L N STO PRE

IR

Project ID: D43 Project Phase: Design

KATHIE CT 289

Description: Improvements to the large culverts and headwalls crossing under Preston Lakes Rd. N PRESTON RD St ate H ighway 2 89

N CELINA PKWY

PRESTON LAKES DR

COUNTY ROAD 59

KRISTINA CT

MARK ALEXANDER CT

Funding: 2024 Bond Funds, Drainage Funds Status: Council approved the resolution to acquire easement at the May 2026 Council meeting. 90% Plans were submitted in June 2026 and design team is addressing comments.

289

COUNTY ROAD 58

289

9

E CARTHAGE RD Carthage Rd

Project Status

Project Progress

S ta t e H ig

h wa y 28

289C

Contact: Scott Harper 469-731-3996 sharper@celina-tx.gov

Project 54 of 69

Estimated Completion

Estimated Total Cost

January 2027

$1,400,000


Preston Rd Lighting Phase 4 (Legacy Dr to Grayson County Line) COUNTY ROAD 60

COUNTY ROAD 107 COUNTY ROAD 138

Project ID: R24 Project Phase: Design Description: This project includes arterial street lighting installation along Preston Rd from Legacy Dr to the Grayson County Line.

STON LAKES C PRE IR

Funding: 2018 Bond Funds, Road Capital Recovery N PRESTON RD PRESTON LAKE S DR

N CELINA PKWY

COUNTY ROAD 58

COUNTY ROAD 106

E CARTHAGE RD

N

COUNTY ROAD 132

COUNTY ROAD 59

Status:

COUNTY ROAD 135

R YD C GA LE

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

COUNTY ROAD 134

Project Status

100% plans completed. On hold until TXDOT's funding is available.

Project Progress

Project 55 of 69

Estimated Completion

Estimated Total Cost

TBD

$740,000


TOMMIE LILLIAN LN

CA

JO HN MPB ELL TRL

Preston Rd Pressure-Reducing Valve and Pressure Plan Adjustment

CAMILLE XING

S PRESTON RD

Project ID: W46 Project Phase: Design Description: Adjustments to intermediate pressure plane in Downtown. Funding: Water Capital Recovery Status:

STARLIGHT CREEK DR

LIG HTCREEK LN

LAUGHLIN LN

This project will be included in the City's 2025 Downtown Water and Wastewater Improvements project.

PRESTON HILLS CIR

Project Status

Project Progress

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project 56 of 69

Estimated Completion

Estimated Total Cost

December 2026

$560,000


Preston Rd Tree Replacement

W FM 455

S DALLAS

Project Phase: Design

N PRESTO N RD

N DALLAS PKWY

Project ID: P35

Description: Evaluation of existing median trees. Design and construction for the replacement of diseased or damaged trees. Modification of existing irrigation system to provide tree bubblers.

W FM 455

Funding: P Y KW

Park Fees 78 24

FM

Status: Construction is delayed to minimize disruption along Preston Road. Start date is pending coordination with TxDOT and the contractor, and is expected in August 2026.

S PRESTON RD

FM 428

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

Project Status

Project Progress

Project 57 of 69

Estimated Completion

Estimated Total Cost

January 2027

$638,200


KALLEE COVE

Public Works Parking Lot - Ph 1

Project ID: B34 Project Phase: Construction Description: The Public Works facility has gravel parking lots. Both City vehicles and personal vehicles are parked on gravel. When City vehicles are washed, they pull them onto a small concrete apron and then park the newly-cleaned vehicle back on gravel. This project will install 100 new concrete parking spaces, a 2,000-foot-long fire lane with two, new controlled access points. This car park will serve both staff and members of the public and will provide the spacing needed for all Public Works-related events and clean-up days in the future. The development of the Public Works facility will be broken up into multiple phases.

COUNTY ROAD 106

Funding: 2022 Bond Funds, 2023 Bond Funds Status: Construction was awarded to Hawk Builders at the April 2025 City Council Meeting. Project is almost completed.

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 58 of 69

Estimated Completion

Estimated Total Cost

September

$3,699,390


Punk Carter Pkwy Right Turn Lane

Project ID: R73 Project Phase: Construction

LN

Description:

IN M O

LO O

SA

PA L

APP A

LN

N PA AR

O

T

Funding:

L TR

S PRESTON RD

The project includes an addition of a right turn lane for northbound traffic on Preston Rd on to Punk Carter Pkwy.

Road Capital Recovery, Roadway Impact (Zone 7) Status: NK PU

Construction is completed. Waiting on submission of final documents to issue the final acceptance letter.

CA

RT

ER

Project Status

QUARTER HORSE LN

SADDLEB RED TRL

D

Project Progress

PK

W

AR TM O

Y

OR

DR

MUSTANG TRL

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project 59 of 69

Estimated Completion

Estimated Total Cost

August 2026

$520,000


Rasor Ranch Wastewater Reclamation Facility Project ID: S37 Project Phase: Design Description: This project includes the future wastewater reclamation facility in Rasor Ranch. Funding: 2021 Bond Funds, 2022 Bond Funds, 2023 Bond Funds, Escrow Reimbursement Status: Approved 100% plans. Project is on an indefinite hold pending wastewater demand.

Contact: Catherine Oduro 469-813-4095 COduro@celina-tx.gov

Project Status

Project Progress

Project 60 of 69

Estimated Completion

Estimated Total Cost

TBD

$67,099,000


PKWY

CALLUM PKWY

N OK

LA

HO

A M

SHADETREE LN

WALK ER

Right Turn Lane on Preston Rd to Lynn Stambaugh Pkwy Project ID: R106

FOUNDERS LN

Project Phase: Design Description:

R D

LYNN STAMBAUGH PKWY

Construction of approximately 500’ of right turn lane from northbound Preston Rd to eastbound Lynn Stambaugh Pkwy.

RE S TON R

2026 Bond Funds

NP

D

Funding:

Status:

E MALONE ST

N TEXAS DR

100% plans are ready. City is awaiting easement acquisition and utility coordination is underway.

Contact: Mina Zamanian 469-545-2403 MZamanian@Celina-tx.gov

W FM 455

Project Status

Project Progress

Project 61 of 69

Estimated Completion

Estimated Total Cost

October 2026

$429,080


Southeast Ground Storage Tank Phase 1 Project ID: W63 Project Phase: Construction Description: This project includes the construction of a new 8 million gallons per day (MGD) Ground Storage Tank on the proposed Southeast Pump Station site. This project is being completed in coordination with the Southeast Pump Station and 54” transmission line. Funding: 2023 Bond Funds Status: The contractor is working on grading the site.

OLD GLENDENNING RD

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

Project Status

Project Progress

Project 62 of 69

Estimated Completion

Estimated Total Cost

July 2027

$13,370,000


Southeast Pump Station

Project ID: W58 Project Phase: Construction Description: This project consists of the construction of a new 25 million gallons per day (MGD) Pump Station on Glendenning Rd west of Coit Rd. This project includes design and construction. This project is being completed in coordination with the southeast ground storage tank and 54” transmission line. This project will also include the decommissioning of the existing Downtown Pump Station. Funding: 2022 Bond Funds, 2023 Bond Funds, 2024 Bond Funds, 2025 Bond Funds Status: OLD GLENDENNING RD

The contractor is working on the pump station site and forced main installation.

Contact: Linda Majeed 972-382-7659 LMajeed@celina-tx.gov

Project Status

Project Progress

Project 63 of 69

Estimated Completion

Estimated Total Cost

June 2027

$60,350,000


W

55

W OA K ST

289

W FM 45 5

W ASH ST

Southeast Transmission Line

Project Phase: Design

on

Rd

E SUNSET BLVD

rest

Description: This project consists of the construction of a new 54” transmission line. This project is being completed in coordination with the southeast ground storage tank and southeast pump station.

SSPPrReEST s t oO n NR R dD

W F M 4 28

FM 428

Project ID: W90

SP

S OKLAHOMA DR

W SUNS ET BL VD

S Bus ines s 2 89

THE RANCH

RD

SP

res

t on

Rd

289C

OLD GLENDENNING RD

Funding: 2022 Bond Funds, 2023 Bond Funds, 2024 Bond Funds, 2025 Bond Funds

W GLENDENNING PKWY 289

COUNTY ROAD 53

Project Status

S COIT RD

OLD LOG TRL

W

OP LO ER T OU

289

S Pres t o n R d

COUNTY ROAD 52

S CELINA PKWY

Status:

E

P OO RL E T OU

CHOATE PKWY

289

Project Progress

Design is 100% complete. Construction contract was awarded to S.J Louis and construction is 10% completed.

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

Project 64 of 69

Estimated Completion

Estimated Total Cost

April 2027

$23,150,000


res NP E

W F M 455

T P e E PECSAt N S can

F M 455

289

SHAWNEE TRL

St

W

a l nut

289

W FM 455

Project ID: R81

COUNTY ROAD 98

W FM 455

Project Phase: Construction 289C

ST

Description: t on

Rd

E ASH

res

The project includes full depth reclamation/ replacement of the asphalt pavement and the installation of sanitary sewer on Sunset Blvd.

SP S OKLAHOMA DR

Funding:

289

S COIT RD

2021 Bond Funds, 2024 Bond Funds, Wastewater Capital Recovery Status: The contractor is working on repairing the irrigation and addressing general grading and clean up before the final walk. WAY

COUNTY ROAD 92

OLD GLENDENNING RD

DEER P ARK

st on

Rd

289

KC ROBINSON LN

S Bus iness 28 9

SS PPRE r e sSTO t o nN RRdD

E SUNSET BLVD

S Pre

W W

Sunset Blvd Asphalt Improvements (Preston Rd to Coit Rd)

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

289

Project Status

Project Progress

Project 65 of 69

Estimated Completion

Estimated Total Cost

September

$4,200,000


lah om

a nsa s

S Ok

s a s SS tA rk

St

a Dr

Dr

i s i a na S Lou

St

rk a n

E Oa

E Elm St

k St

S A

a Dr S Ok la h om

a Dr isia n

E Ash

Description: Schematic design for Sunset Blvd from Oklahoma Dr to FM 428. Rd t on

SP

S B usines s 28 9

BLVD W SUNSET W Sun set Blvd

Project Phase: Design

res

Olymp ic Dr

Project ID: R113

St

S OKLAHOMA DR

S Ohi

o St

a k St

S L ou

Dr z ona C o l o r DO S ado S T t

W Ce dar S t

W O

S CSOLORA

S ALABAMA DR

TOLLESON DR

DR STEFHANIE Stefhanie Dr

y Pk w

Zion

W Elm

Sunset Blvd Schematic – Oklahoma Dr to FM 428

S Te xas St

S Uta h St

W C e d a r St

S A r i z o S AR n a D r IZON A DR

W ASH ST S Alabam a St

Ye llow stone D r

S Ari

SK

a b am a

S Al

Stefhanie Dr

W FM 428

T o l l eson Dr

Way

in St

O ak St

289

Funding:

Road Capital Recovery Status: Schematic for at grade crossing complete. BNSF stated that an at grade crossing will not be allowed. Design amendment has been requested to identify implications of split grade crossing over BNSF.

EST ON R

DS

Pre

st o

nR

d

28 FM 4W F M 42 8

S PR

289

289

Rd

S Busin ess 289

Project Progress

st on

Project Status

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project 66 of 69

Estimated Completion

Estimated Total Cost

December 2026

TBD

S Pre

County R oad 5 5

W FM 428

8

Ho

t Sp r in g s

W E

m St W ELlM ST

WWOAK ST

W Ash St

W FM 428

u n s et B lvd

W Elm St

W Ma


Tudor Pl at FM 1385 Intersection Improvements Project ID: R116 Project Phase: Design Description:

FM 1385

The project includes pavement widening of Tudor Pl to accommodate two 11’ lanes (additional 5’ of pavement width) at the westbound approach of the FM 1385 intersection of approximately 350 linear feet. TUDOR PL

Funding: 2024 Bond Funds Status: Awaiting for the 100% design plans.

PARVIN RD

Contact: Linda Majeed 469-813-4189 LMajeed@celina-tx.gov

Project Status

Project Progress

Project 67 of 69

Estimated Completion

Estimated Total Cost

December 2026

$370,000


TxDOT Frontier Pkwy (Preston Rd to Custer Rd)

FM 2478

ROSELAND PKWY

Project ID: R41 Project Phase: Design Description:

WELLS RD

SC OIT RD

N HILLS CIR STO E PR

EO WN SB YP KW Y

TxDOT will be reconstructing the existing asphalt roadway to four lanes of curbed concrete road with underground drainage system and sidewalks from Preston Rd to Custer Rd.

ERVIEW TRL WAT

WORTHINGTON WAY

S PRESTON RD

PUNK CARTER PKWY

Funding:

E FRONTIER PKWY

Road Capital Recovery Status: 100% plans approved. Utility locations are to be completed by May 2025. TxDOT is waiting on funding to start construction. TxDOT has not provided a timeline for construction to start.

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

Project 68 of 69

Estimated Completion

Estimated Total Cost

TBD

TBD


Wilson Creek Park - Phase I

Project ID: P31 S Co i t R d

Project Phase: Design

Oak Hill Ln

Description:

S COIT RD

Wilson Creek Park is a 100-acre park located at the northwest corner of Sunset Blvd and Roseland Pkwy within the Parks of Wilson Creek subdivision. This park is currently undeveloped and will be constructed in multiple phases. Phase I of the project consists of the design and construction of approximately 30 acres of Wilson Creek Park to include two multi-use sports fields complexes, a pond, irrigation, and the first two lanes of the Wilson Creek Park driveway. This phase of the project also includes floodway reclamation and coordination with U.S. Army Corps of Engineers. This project development will follow the approved Wilson Creek Park Master Plan. Funding: 2022 Bond Funds, 2023 Bond Funds

C

ou

nt y

S Co i t R d

COUNTY ROAD 92

County Road 92

Ro

Status:

ad 92

BLVD E SUNSET C o un ty Roa d 92

Construction in progress. Issues with obtaining necessary water from North Texas Groundwater Conservation District has led to project disruption. Proceeding with original construction plans. Waiting for additional legal direction for next steps.

S Coit Rd

Contact: Richard Herrera 469-290-7346 RHerrera@celina-tx.gov

Project Status

Project Progress

L

ye afa

tte Dr

Project 69 of 69

Estimated Completion

Estimated Total Cost

January 2027

$12,200,000