Steps to restoring power Restoring power after a major outage involves steps for safely getting the most members restored in the shortest amount of time. Our plan is based on these priorities:
Step 1: Transmission structures and lines that supply power to one or more transmission substations are restored first. These main delivery lines receive first priority because they serve tens of thousands of people. Step 2: Next are distribution substations, which “step down” (reduce) voltage from transmission lines so it can be distributed to thousands of members.
1 Blue Ridge-0121.indd 17
2
Step 3: Main distribution supply lines (the ones you see on poles along roads) are targeted next. Step 4: The final power supply lines, called “tap lines,” are restored next. These are lines coming off main distribution lines. Step 5: Damage can also occur on the service line leading from the transformer pole into your home. This could be why your neighbors have power and you don’t. Outages can be reported 24/7 via the mobile app, by calling 1-800-448-2383, or by using outage texting.
3
4
5 12/10/20 1:45 PM