Archer Western Construction Norman Water Reclamation Facility Project
C O M P A N Y O V E R V I E W
Archer Western Construction Norman Water Reclamation Facility Project Archer Western Construction Begins Wastewater Treatment Plant Project in Norman, Oklahoma
David Nine, Archer Western Construction Project Manager for the Norman Wastewater Treatment Plant Project, discusses how the company became involved with the project and explains how the project will benefit the city once it is completed. Written by: Lindsey Ryan
Produced by: Tom Venturo
3
ARCHER WESTERN CONSTRUCTION NORMAN WAT E R R E C L A M AT I O N FA C I L I T Y P R O J E C T
Activated Sludge Aeration Basin with Blower Pipe and Sanitare Diffusers
T
he Norman wastewater system is owned, maintained and operated by the city of Norman, Oklahoma, and in November of 2013, the Department of Environmental Quality mandated that the treatment facility be upgraded. This $60 million project, consisting of an expansion to allow for increased water flow, an ultra violet disinfecting plant and overall rehabilitation of the existing infrastructure, was bid out to six different pre-qualified contractors and after review and consideration of all bids, the project was awarded 4
February 2015
to Archer Western Construction (a subsidiary of the Walsh Group). David Nine, Archer Western Project Manager for the Norman Water Reclamation Facility Project, explains that Archer Western Construction had been doing smaller projects in Oklahoma for about five years and when the company caught wind of this project in 2013 while it was in its early design stages, they knew this could be their chance to launch their operations and establish themselves in Oklahoma. After putting together a winning strategy and providing their bid, the company was awarded the
CONSTRUCTION
New Centrifugal Blowers installed
project in April 2014. “It worked out great; it’s very seldom do you identify the project a year out, pursue it, chase it, win and get to go build it,” states Nine.
be working to expand the treatment capacity from 16 mgd to 32 mgd, adding two new clarifiers, 3 new activated sludge aeration basin, new sludge pump station and dewatering facility, new screenings About the Project facility and odor control. Prior to The Norman Water Reclamation beginning that work, Nine explains Facility expansion is the largest that Archer Western Construction wastewater treatment plant is first working to complete another expansion ever awarded in the component of the project, the UV state of Oklahoma and the project disinfecting plant. is being funded by the Oklahoma The UV Facility includes the UV Water Resource Board (OWRB), who basin, UV building and Post Aeration granted the city of Norman a $50 Basin, 3000 lf of 66” pipeline and million construction loan. outfall structure, all of which must Archer Western Construction will in operation by the early completion w w w. W a l s h g r o u p . c o m 5
LET’S SOLVE YOUR BIOLOGICAL TREATMENT NEEDS
RELIABLY. LET’S SOLVE
WATER.
xyleminc.com |
sanitaire.com/us
Sanitaire — a Xylem brand, is a proud supplier to the Norman WWTP and would like to thank the municipality for their continued support of our Sanitaire aeration solution. Xylem’s Sanitaire brand is an industry leader in wastewater treatment solutions for municipal and industrial wastewater treatment applications. Sanitaire offers complete biological wastewater treatment solutions, including diffused aeration, sequencing batch reactor systems and membrane bioreactor systems. Sanitaire’s highly qualified experts will provide the best possible solution for your wastewater treatment projects. To learn more about all Sanitaire has to offer you, call (414) 365-2200 or visit www.sanitaire.com/us.
Xylem is a global water leader deeply involved in every stage of the cycle of water, transporting, treating, testing and analyzing, then returning it to the environment. Xylem’s brands produce highly efficient products and systems that require less maintenance, use less energy and provide environmental benefits to users and communities. Doing business in more than 150 countries, the company plays an important role in improving quality of life, helping communities to grow, farms to prosper and industries to thrive. Xylem’s treatment brands include:
SUPPLIER PROFILE
XYLEM
ylem — a premium applications solutions company dedicated X exclusively to solving our customers’ most challenging water problems — was formed from ITT Corporation’s spinoff of several strategic business segments in October 2011, namely the Water & Wastewater, Residential & Commercial Water, Analytics and Flow Control businesses. As a stand-alone company, we are a world leader in water technology, providing equipment and services for water and wastewater applications with a broad portfolio of products and services that address the full cycle of water — from collection, distribution and use to its return to the environment. Through our signature citizenship program, Xylem Watermark, we bring clean water, sanitation and hygiene education to schools and communities in emerging markets, and respond with water solutions when disaster strikes around the globe. Website: www.xyleminc.com
ARCHER WESTERN CONSTRUCTION NORMAN WAT E R R E C L A M AT I O N FA C I L I T Y P R O J E C T
milestone of November 14, 2015. Currently the treatment facility has primary and secondary treatment but no disinfection, so this is an additional treatment step which will allow the city to re-use that water in the future. In addition, $10 million is going towards odor control throughout the entire plant. The UV plant and odor control are major components to the project and are extremely beneficial to the city of Norman. Nine states, “Once the UV Facility is completed, a nearby composting facility will start using the reclaimed water for their composting operations so the city will be able to re-use this water.” Archer Western Construction will build about 75% of the project itself, only sub-contracting about 25% of the job. The treatment plant is currently in phase 2 out of 3 and is
CONSTRUCTION
expected to be completed on time in November, 2016. Looking forward, the treatment plant is expected to pump the reused water to Lake Thunderbird where Norman gets its drinking water. Community Support The Norman Water Reclamation Facility serves the city of Norman, a population of about 100,000 people, and the community as a whole has been extremely supportive of the project. “This is unique project because the citizens in the city of Norman voted 78% in favor of this expansion so the whole community is really behind the project,” Nine says. On November 5, 2014 the mayor and city council were on site at the project for a publicized ribbon cutting event to launch the project
“It worked out great; it’s very seldom do you identify the project a year out, pursue it, chase it, win and get to go build it” – David Nine, Archer Western Project Manager for the Norman Water Reclamation Facility
w w w. W a l s h g r o u p . c o m
9
ARCHER WESTERN CONSTRUCTION NORMAN WAT E R R E C L A M AT I O N FA C I L I T Y P R O J E C T
New Centrifuge Thickening Equipment
Custom Conveyor Corporation Proud Archer Western Material Handling Equipment supplier for Norman, OK & Lubbock, TX Norman, OK WRF Shaftless Screw Conveyors • Screenings • Sludge
Lubbock, TX Cake Loading Facility • Shafted Conveyors • Storage Hopper • Truck Loading
Rogers, MN | 763.367.6200 | customconveyorcorp.com
CONSTRUCTION
Company Information INDUSTRY
Construction HEADQUARTERS
Irving, Texas FOUNDED
2014 EMPLOYEES
60
and show their support. Also, since the University of Oklahoma is in Norman, Nine explains that Archer Western Construction has even hired three college graduates to work as engineers for the project. Overall the project will be a great resource for the community and an environmental step towards sustainability.
REVENUE
$50M
w w w. W a l s h g r o u p . c o m 1 1