Cap DC España, a subsidiary of CAP Ingelec, provides invaluable local knowledge and project management to international clients in Europe and Africa
A
ccording to the data analysis specialist Arizton, the data centre/colocation market in EMEA was worth around US$14bn in
2019. It’s a burgeoning market, driven by factors like the EU’s General Data Protection Regulation (GDPR) 04
and rapid adoption of internet-based services among businesses in the Middle East and Africa region. The Cap DC Group, a subsidiary of the leading French Cap Ingelec brings together local engineering firms in Southern Europe and Africa to build data centres to meet this demand, and has been ranked among the top 15 global data centre engineering firms by Arizton. While its core business is data centre engineering, increasingly it is offering its clients in southern Europe and francophone Africa the option of EPC or turnkey construction contracts, says its Managing Director Antonio Ríos Suanzes. Antonio came on board in 2017 to set up the company’s headquarters in Madrid. In that time his team has grown to eight, turnover to €5.5m, and revenue is targeted to reach €10m by 2022.
05
www.c a p- d c. com
Where real estate meets the cloud 1. Amsterdam, The Netherlands 7.5 ha | 40 MW (pot. 80 MW) 2. Frankfurt, Germany 3.5 ha | 65 MW 3. Paris, France 2.0 ha | 40 MW 4. Milan, Italy 2.0 ha | 40 MW 5. Madrid, Spain up to 10.8 ha | 49 MW
datacenterCE@goodman.com
ce.goodman.com
Powered shell opportunities in Continental Europe At Goodman we deliver high-quality built-to-suit powered shell in record times, which will help you meet your ambitions and growth needs. Accelerate your data center development through our real estate solutions and knowledge.
“Madrid is seeing strong growth in tier
tech giants (GAFA) have no foothold yet
2 of the European data centre market
and very few pan-African colocators
thanks to the increase in subsea cables
are active.
reaching the Iberian peninsula,” he says.
“The market is still mostly driven by
“We foresee huge growth in Madrid and
telcos like Orange, or by the public sec-
Barcelona over the coming years.”
tor,” says Antonio. “For example, we
Cap DC has also begun its expan-
are working for the national data centre
sion into Milan, he adds, and Microsoft
agencies in Senegal and Guinea. The
announced recently that it will build data
size of the data centre market in Africa
centres in Greece, while Cap DC deliv-
is currently far smaller than in Europe,
ered two colocation projects in Turkey
but we consider that with rapid popula-
in 2020.
tion growth and the real innovation
With the southern Europe data centre
capability across the continent, it will
market set fair, he notes that Africa
equal the rate of development in Europe
is a completely different market. The
within five years.”
Madrid company has six offices in Africa
He is encouraged in this view by
from Morocco to Senegal to Ghana and
African leadership in mobile payment
Cameroon. In these markets, it’s all about
and its innovations in e-agriculture and
potential. Apart from South Africa the
e-health business.
www.c a p- d c. com
07
CAP DC
08
Wherever it is to be built, time to market is the most important consideration
cater for the unknown final requirements of the final client.
for data centre operators and this
“In our view, the technical solution for
is where Cap DC derives a distinct
a data centre client is a combination of
advantage from its deep engineering
merging operator requirements (some-
know-how and the resources of
times pre-defined in the best-practice
Cap Ingelec.
policies of the company) with the skill
Flexibility and modularity are its priori-
to adapt these requirements to local
ties. Power usage effectiveness (PUE)
regulations as necessary, and to validate
driven by modern cooling systems such
construction feasibility in a short time-
as direct and indirect free-cooling and
frame,� he says.
choosing the right location are always
The contracting model developed
important, but design flexibility must
by Cap Ingelec and Cap DC has been
a major growth factor since 2015, Antonio feels. “The difference in approach between a general contractor and an engineering specialist is clear. The turnkey contract model we offer our clients focuses on time-to-market. Between our group infrastructure and our local representatives, we can provide full governance of the projects, including licensing, securing power supplies and managing all legal issues: this enables us to commit to a budget and schedule with the client and stick to it. “This model has helped many of our clients not only to design but to deliver their
“ The size of the data centre market in Africa is currently far smaller than in Europe, but we consider that ... it will equal the rate of development in Europe within five years” — Antonio Ríos Suanzes, Managing Director, CAP DC España
data centres on time. We are very gratified that more clients are trusting us with the full design and construction of their projects. It’s convinced us that this is the construction model that fits this market.” For Antonio Ríos Suanzes, the key to an effective turnkey solution in the data centre industry is to have the right collaborators, partners and suppliers in place. A good example is the fire protection system, which needs to be planned at an early phase of the project to ensure a system that is fit for www.c a p- d c. com
09
CAP DC
“ We consider that this pandemic has boosted digitalisation more than any new product or marketing campaign” — Antonio Ríos Suanzes, Managing Director, CAP DC España purpose and protects the data centre through its entire lifecycle. Taking into account every possible detail during the project planning stage 10
means less need to make changes later. Making changes to the routing of the pipe network, for example, could disrupt
are delighted to bring to the client the
operations. Also, fire suppression in
quality and performance of our suppli-
data centres can be challenging due
ers.” Close communication across
to the high airflow and the increased
the entire value chain is his mantra:
power density of servers. The upgraded
“If one partner has a problem, the others
FM Standard 5560 incorporates new
have a problem too.”
fire test protocols for data halls and
Strategic partners are equally impor-
subfloors: long-term Cap DC supplier
tant. Private equity and hedge funds
Marioff provides a high-pressure water
are increasingly interested in data cen-
mist solution, a very reliable fire protec-
tres as an alternative to their logistics
tion system focused on total cost of
investments. The global property group
ownership (TCO) and with OEM sup-
Goodman is setting the standard on this
port 24/7, says Antonio.
shift of emphasis and is a key partner for
“We manage construction but we are not a supplier company, so we
Cap DC. “Goodman has the financial resources
11
E X E C U T I V E P R O FILE :
Antonio Rios Suanzes Title: Managing Director
Company: CAP DC España
Industry: Construction
Location: Madrid
Antonio Rios Suanzes is Partner and Managing Director at CAP DC España, responsible for the company development in Spain from its creation in 2017. He holds two master’s degrees in Engineering and Corporate Finance. During his three years at CAP DC España, he has overseen the growth of the company from one to eight employees and seen the turnover increase by € 5.5 million. Over this period of time, Antonio has also grown as a leader and acquired essential managerial skills at the young age of 33. Antonio has broad experience in international projects and reports directly to the group CEO based in France. www.c a p- d c. com
Reliability without compromise Fires in modern data centers are harsh; not only in their direct damage, but also indirect damage to business continuity. Prepare against fire with Marioff HI-FOGÂŽ: a high pressure water mist fire protection system that uses a small amount of water at the seat of the fire; thus minimizing damage and downtime.
Your safety is our expertise.
“ Goodman has the financial resources and strong local teams in key locations” — Antonio Ríos Suanzes, Managing Director, CAP DC España
13 and strong local teams in key locations
has had to face the challenges posed
such as Frankfurt, Paris, Amsterdam,
by Covid-19, though the situation has
Milan and Madrid,” says Antonio. “Its
boosted the data centre market.
group strategy is to purchase a plot,
“We consider that this pandemic has
secure the power infrastructure (a
boosted digitalisation more than any
specialised process in a complex and
new product or marketing campaign,”
regulation-fraught environment), and
says Antonio. “We expect growth in
then invite interested parties. Once
digital services that will require more
the data centre operator is on board,
investment in data centres and faster
Goodman will support construction
development of tier 2 cities like Madrid,
and rent it to the operator. This model
Monaco or Bordeaux. Internally, in Cap
speeds up delivery by outsourcing plot
DC we were prepared for a ‘smart work’
selection and power due diligence. In
period and we are very proud of how the
Madrid, we are talking 6-12 months
team has reacted to this situation. The
saved on ready-for-service date.”
technical team has been working from
Throughout 2020, every industry
home and the construction team have www.c a p- d c. com
CAP DC
“ The turnkey contract model we offer our clients focuses on time-to-market” — Antonio Ríos Suanzes, Managing Director, CAP DC España
14
adapted their schedule to keep the business running and minimize the impact.” The dramatic uptick in demand will not decline when Covid is finally vanquished, he believes, as business consolidates the efficiencies it has been forced to adopt. In a city like Madrid, securing power supply for new data centre capacity at strategic locations can be a limiting factor, he notes: “We have identified power supply and infrastructure between substation and data centre as a red flag that was delaying or even withdrawing projects. To tackle this, since 2018 we have offered a consulting service to deal with the electricity provider, securing power alongside a specific turnkey contract to develop this infrastructure. We are very happy with how this has impacted our business and we have been growing turnover every year.” This success is getting recognised: Cap DC recently received an award as the leading company in Data Center Construction in Spain in 2020 from La Razón newspaper, one of Spain’s most influential.