Paradigm Paradigm shift shift The first phase of a luxury new residential block is rapidly rising from the ground in NoMa, the fastest growing neighborhood in Washington DC. Hosein Omidi-Shal, project manager at Paradigm Construction, explains how the work has been accelerated ahead of schedule by creative task assignment
Paradigm Construction
1st Street (south from M)
Paradigm Construction
N
oMa, which stands for north of to the decor. There will be a well-stocked Massachusetts Avenue, is one library with a music practice studio above of Washington DC’s fastest it, a lounge, gourmet kitchen, media suite growing neighborhoods. and small theatre. The on-site gym will Located just north of Capitol have a fully equipped fitness suite as well Hill and Union Station and enjoying as a health promoting ‘green wall’ and a spa. good metro, rail and bus links, it has Throughout this level, the interior design been transformed over the last few years and the attention to detail speak of quality. from a blighted industrial area to a busy Among the many features of interest are and desirable residential and business glass shield walls and ceiling in the lobby, destination. intricate water features and imaginative One of the rising jewels of the LED lighting. The twelve stories above will neighborhood is Archstone Square 673, house 469 luxury residential units. an ambitious Class A residential high-rise “The building has a very elaborate façade,” tower that is taking shape said Hosein Omidi-Shal, on what was originally a “and this is a combination of precast concrete and large parking lot on 1st and M streets. With 13 stories brick in four different colors; above ground, a roof top it’s a very complex piece of swimming pool and three construction, waving in levels of underground and out as it rises up the parking, it’s designed for building.” luxury living and aimed at Manag ing complex Value of construction contract residential high rise young professionals. construction projects is “As a class A building, something that Paradigm it will contain firstclass amenities,” explained Hosein does very well, and the company has Omidi-Shal, project manager at Arlington- built a solid reputation around the region based Paradigm Construction, the main for applying engineering knowledge and contractor for the project. Designed in a C experience to construction issues, reducing shape, the building focuses around a central both time schedules and costs. On this outdoor courtyard that provides a range of construction project, the relationship lifestyle features for the residents, including between Paradigm and Archstone has been fountains and water features, seating and close, more a partnership and a sharing of dining areas, a BBQ and an open air theatre. ideas. “Archstone invited us to come in at the Inside the building, the first floor is design stage about four years ago to advise largely dedicated to amenity space and the on the construction of the building,” Omidifinishing touches are currently being made Shal said, “to recommend how, strategically,
$100
million
• The Best of Everything for your prestigious Project • Mastered Craftsmanship • Granite & Marble Kitchen Countertops, Kitchen Cabinetry, Vanities, Fireplaces & More
6202 Gravel Avenue, Alexandra, VA 22310 Office: 703 313 7900 | Fax: 703 313 9821 www.springfieldmarble.com
inspired Your weekly digest of business news and views www.bus-ex.com
Paradigm Construction
Rooftop pool
the proposed project could traditional foundations we suggested using a four be brought together, and foot thick concrete mat how cost savings could be as a footprint beneath the made.” entire building, and this A property developer in Drilled to a depth of 50ft its own right, Paradigm was would minimize cracks and movements in the future.” awarded the $100 million construction contract on In preparation for 7 July 2010 and began work immediately. excavating the ground for the three levels of “We’re now 70 percent complete,” he subterranean parking, as well as four feet of continued, “and we expect to finish by the concrete foundations, the company drilled end of September this year, which is roughly 13 wells to a depth of about 50ft, drying the soil to safe levels by pumping the water out. four months ahead of schedule.” One of the issues Paradigm examined The schedule for construction then moved from the design stage was the poor nature quickly. By the end of October the concrete of the soil, and the implications for the build. was being poured into the foundations and “The soil beneath the site was waterlogged,” the concrete skeleton of the building was explained Omidi-Shal, “so rather than use topped out by July 2011.
13 wells
At this stage, the complexity of the project increased, as Paradigm put in place the strategy it had devised for completing the outer walls and weather proofing the building to an accelerated time schedule. There were a number of challenges involved, one of the big ones being the undulating precast concrete sections so carefully designed for the outward facing walls of the building. It wasn’t, however, the waving nature of the sections that created the problem. “In a normal brick construction project, you would begin building the brick facade while the concrete structure is being erected so the walls follow the concrete up and wrap the building completely. We couldn’t do that,” Omidi-Shal said. “We couldn’t start the masonry work until the precast concrete wall sections had been installed. And because of the weight of the precast sections, they could not be installed until the building was completely topped out and the structure had reached optimum strength to be able to carry the load.” It was very much an engineering jigsaw puzzle with an extra dimension – time – where any time added to the project would add considerably to the overall cost. The solution that Paradigm devised involved
collaborating with the contractors and imposing an innovative schedule of work that broke the normal routines. “We did this by bringing the masonry contractor in to begin work on the inner courtyard where there were no precast elements. At the same time the concrete contractor began installing the precast elements on the outward facing sides of the building,
“We expect to finish by the end of September this year, which is roughly four months ahead of schedule”
Paradigm Construction
1st Street: The big screen
working on two façades simultaneously rather than one at a time. Once they had finished, the masons then wrapped around the building.” The interior of the project has also required some innovative scheduling. With the courtyard-facing walls completed and weather proofed first, work was able to begin on fitting out those apartments while the outward facing walls were still under construction. “The schedules we’ve visualized for this project have worked well,” Omidi-Shal said. “And we believe we’ve saved around three months on the façade and concrete work.” The interior is also in good shape and the amenity space almost complete. The
plan is to open the leasing office in March, and for the first residents to move in by late May, well ahead of schedule. Omidi-Shal puts much of this success down to good working relationships. “We are working very closely with Archstone, which has been excellent in providing the information we need, answering our questions and making decisions in a timely fashion,” he said. “But I also have a good team working for me, and they have been managing the work pretty well.” For more information about Paradigm Construction visit: www.paradigmcos.com