Senate Quarterly Report, Faculty of Dentistry, July- September 2023 General
The Faculty has made progress in the following key areas in the last 3 months: Infrastructure: Infrastructure upgrades have started in the following places: Upgrade of Mitchell’s Plain Entrance and Reception: Completed August 2023 Upgrade of A Floor Postgraduate Student Room at Tygerberg: completed September 2023 Upgrade of D Floor Student Common Room at Tygerberg: completed September 2023 Upgrade of D Floor Staff/Student Cafeteria: phase 1 completed September 2023, Phase 2 (kitchen) due for completion end November 2023 WIFI Upgrades at Tygerberg: completed end July 2023
1: Postgraduate Work Lounge
2: Dentistry Slow Lounge
Undergraduate Matters o o
Applications for the 2024 intake for BOH is closed and stands at 5308 Applications for the 2024 intake for BDS is closed and stands at 5169