GOAL 15: Seaplanes: Facility and Service

Key Issues

 Design  Funding  Construction 1. Obtain permits 2. DECISION: Funding and Design 3. Complete construction 4. Ribbon-cutting and 1st Flight

Responsibility: City Engineer

6/22 6/22 TBD TBD

June 2022 Update

• A request has been made to the consultant to provide a proposal for the engineering design and permitting of the seaplane base. Proposal received. Engineering recommending additional proposals be solicited. • Proposal for the relocation of the shuffleboard courts was presented at the June Conference

Agenda meeting. Direction was obtained to continue with preliminary design of new shuffleboard courts.