JOHN ADAMS ELEMENTARY AND EARLY CHILDHOOD CENTER
BUREAU VERITAS PROJECT: 148303.21R000-001.354
Key Findings
Exterior Walls in Failed condition.
Priority Score: 89.9
Brick, 3+ Story Building Transport Facility - System Wide Building exterior
Plan Type: Performance/Integrity
Uniformat Code: B2011 Recommendation: Repair in 2021
Cost Estimate: $45,600
$$$$
The exterior brick wall on the elevation and back of the building was observed with damage, appeared to be caused by water/moisture intrusion. - AssetCALC ID: 3246881
Boiler in Poor condition.
Priority Score: 86.8
Gas, HVAC, 1260 MBH Transport Facility - System Wide Boiler room
Plan Type: Performance/Integrity
Uniformat Code: D3021 Recommendation: Replace in 2022
Cost Estimate: $50,800
$$$$
Boiler exhibit significant wear and tear as well as rust that may compromised internal components (electronics). AssetCALC ID: 3229074
Recommended Follow-up Study: Civil, Site Drainage Civil, Site Drainage Transport Facility - System Wide Building exterior Uniformat Code: P2032 Recommendation: Evaluate/Report in 2021
Priority Score: 81.9 Plan Type: Performance/Integrity Cost Estimate: $7,000
$$$$
Building personnel informed of water damage, water intrusion into the building coming from the front of the building and streaming on the left elevation due to the slope of the terrain. - AssetCALC ID: 3247061